Found this site while trying to get more details on why Juniper St Complete street still hasn't started:
Lots of details about many project!
5th Street Complete Street
Design finished September, and construction expected to start Feb 2022
https://atldot.atlantaga.gov/projects/5th-st-complete-street
Howell Mill Complete Street
Design Finished October, and construction expected to start June 2022
https://atldot.atlantaga.gov/projects/howell-mill-complete-street
Juniper Street Complete Street
Design Finished October 2020, and construction expected to start Feb 2022
https://atldot.atlantaga.gov/projects/juniper-street
Monroe Drive Complete Street
Design expected to finish September 2023
https://atldot.atlantaga.gov/projects/monroe-dr-complete-street
Piedmont Avenue Complete Street
Design finished July 2021, construction expected to start December 2021
https://atldot.atlantaga.gov/projects/piedmont-ave-complete-street
Spring and W Peachtree Quick Build enhancements
Design finished October, construction expected to start January 2022
https://atldot.atlantaga.gov/projects/w-peachtree-st-spring-st-qb-complete-streets
15th Street Extension
Design finished July, construction expected to start Feb 2022
https://atldot.atlantaga.gov/projects/15th-st-extension
In theory a lot of really important projects will be ramping up soon in Midtown