Got a section of the L1 slab poured on east side of pit this week. Have some of the L1 walls now poured in SE corner. Steel rebar for L1 slab on west side of pit nearly done so should see that poured next week. Still no steel rebar for the L2 slab around the tower crane base.
A couple more of the L1 walls in SE corner and along south wall are now poured. Poured another section of the west side L1 slab. Still haven't finished the L2 slab around tower crane as of yet. They have been working on the drainage system and I suspect sump pit for water collection.
Looks like they finally poured the L2 slab around tower crane base. Have the NW corner L1 slab steel rebar installed and it looks ready for the concrete pour.
Now forming and installing steel rebar for the L1 slab on the north side of pit. This is the side under the tower and appears where the underground parking entrance will be located.
Ground floor slab poured now along south side of pit. This will be surface parking and driveway entrance side to the building. Still finishing up the L1 walls and posts under the building on the north side of site.
Some of the ground floor wall forms have started going up in the SE corner. Don't appear to have completed the ground floor slab pour yet in the north end or the NW corner.
In typical Drewlo fashion they have slowly made some progress on forming ground floor walls in the SE wing. Have started a few wall forms in the center of the building. At this rate they will still be forming the ground floor walls on the west side and north end at the end of April.
Pouring the 2nd floor slab of the SE wing today. Have made progress forming and pouring 1st floor walls and posts along the north section of the building.