Slowly making progress on the L1 level walls and posts towards the east side of pit. Doesn't appear that they have poured any of the ground floor slab yet on the west side.
Looks like they have finally poured some of the ground floor slab on the west end of pit and have forming up for the first ground floor walls there. Still working on the L1 footings and posts and walls on the east side of pit thou.
First ground floor walls are now poured on the west end and have now poured another section of the ground floor slab in the SW corner. Still working on the footings and L1 posts and walls on the east side of pit.
Last edited by jammer139; Nov 28, 2022 at 2:37 PM.
They were completing the ground floor slab pour today along the south side of the pit. Still have alot of forming to do along the northeast side of the pit to complete the underground level.
Ground floor slab is now completed. Have around 40% of the ground floor walls and posts poured on the west end of this project. Given its Drewlo will likely take another 6 weeks to complete the ground floor walls and posts.
I reckon that the Great Pyramid of Khufu was built faster than some Drewlo buildings.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Have maybe 60% of the ground floor walls and posts poured now and have started forming for 2nd floor slab on the west end. Have not even got forming up yet for ground walls and posts on the east end at this point.
They have poured some of the 3rd floor walls and posts on the west end now. The rest of the 2nd floor walls and posts are now poured. Forming for 3rd floor slab continues in the center section.
Looks like they may have finally finished forming and pouring the 3rd floor walls in the NE corner. The 4th floor slab may has also finally been poured on the west end as they have now started putting up 4th floor wall forms. I suspect Drewlo is directing the lions share of their concrete forming crew to the 16s Talbot St building in an effort to get it topped out before the end of the year. Hopefully once that happens the concrete forming crew can focus on this 11s building thru next winter and spring.
They have finished pouring the 4th floor slab on the west end and are forming and pouring some of the west end 4th floor walls. The east end is now wrapping up the 4th floor slab and starting forming for the 4th floor walls.
They have finished pouring all the 4th floor walls and posts now and have poured some of the west end 5th floor slab as they have 5th floor wall forming started on that end. Still have the eastern half of the 5th floor slab to form. They should get a boost of manpower in a couple of weeks when the concrete forming crew on Talbot St finishes their work there.