Quote:
Originally Posted by electricron
DART wanted to build the Green Line in a tunnel under Love Field and actually have a light rail station at the Love Field terminal. FTA said no, even after DART promised to pay for all the extra expenses over the alternate route which DART eventually built.
|
FTA didn't think it was worth the cost. DART paying for it doesn't make a difference, if they're being poor stewards of the project funds, that puts the whole project (and FTA's contribution) at risk.
https://www.progressiverailroading.com/r...-include-Dallas-Love-Field-tunnel--12990
Quote:
Originally Posted by electricron
So please do not even suggest the FTA does not look at how much light rail lines cost.
|
I never, ever claimed that. I'll thank you not to try to put words in my mouth (though you failed spectacularly).
They look at the tradeoffs involved. Sometimes they think costs are worth it, sometimes they think they're not.
Quote:
Originally Posted by electricron
Given a choice, they more than likely will choose the cheaper option. Because they do look at costs.
|
Then we're not getting any tunnels whatsoever. Because a purely surface grade rail is the cheaper option. Heck, if that were the case then the FTA would never in its history have ever approved a light rail project, because buses are always cheaper.
But the truth is they look at costs _as part of a whole cost-benefit tradeoff_
Quote:
Originally Posted by electricron
The best way to get the FTA to approve the longer tunnel and associated costs is to show that ridership increase more than pays off the extra costs. Or outright lie to them. Good luck with that!
|
The ridership, the operational efficiencies, etc.
In other words, all the factors that CM/ATP _are already looking at when making that decision_.
There's literally a whole matrix in the document I already linked
http://capmetrotx.iqm2.com/Citizens/FileOpen.aspx?Type=1&ID=1867&Inline=True
page 120