Here's "the 834." There was some sort of issue with excavating the west side of the site, or doing the foundation work, so even though most of the building is up 10 floors already, the west side of the podium and tower is not yet complete.
Quote:
Originally Posted by Noss
...the West side of the building was muddy and slowed down progress in terms of pouring concrete (which is now underway).
|
Quite a bit of the concrete for the west side of the building (the podium and the tower) has not yet been poured. There is exposed rebar on every floor on the west side of the tower where additional floorspace has yet to be poured. Here are some photos I took today.
See the rebar sticking out of the floors. An extra 10 to 20 feet of floor slab still needs to be put in place on this side.
The west side of the tower.
There is supposed to be a four storey podium (plus foundations) here between the tower and the red building. This is what will support the extra floorspace on the tower.
The east side looks good.
Work continues.