Old Posted Feb 3, 2015, 12:23 AM
93JC 93JC is offline
Registered User
 
Join Date: Jul 2006
Posts: 932
Regarding Bankers Hall, a post from four years ago:

Quote:
Originally Posted by 93JC View Post
The auditorium is built beside the foundation wall, which is right at the property line. Bankers Hall's foundation doesn't extend below the street.

Hypothetically you might able to repurpose part of the auditorium as a subway station but it would entail major modifications, the least of which would be punching out a large portion of the foundation wall. I'm not a structural engineer but I'd guess that would not be a simple task...


On the other hand there really are tunnels underneath the Municipal Building and Olympic Plaza.
It's not even close to being roughed-in at Bankers Hall; it is at the Municipal Building. Tunnels really are already built below it and Olympic Plaza, just waiting to be connected to some day...
Reply With Quote
     
     
  #702  
Old Posted Feb 3, 2015, 12:29 AM
Blue_Cypress's Avatar
Blue_Cypress Blue_Cypress is offline
Snarkotron
 
Join Date: Sep 2006
Location: Mount Pleasant, Calgary
Posts: 2,580
Quote:
Originally Posted by s211 View Post
Not exactly. The lobby area just to the east of the auditorium is where the building would connect to a subway station entrance. There is no station rough-in within the Bankers Hall perimeter, from my prior experience with this project.

In short, there's a design allowance for what could then be a hallway connection to a station, but no rough-in for the station itself.
Not a station, but certainly convertible spaces. I often times wish the 8th ave tunnel project would go ahead just so I could have the opportunity to work on it. I think we'd need an initiative like the Transportation Project Office again to make it a reality.

I've got drawings for the portion under city hall. Maybe I'll dig those up this eve.
__________________
"The ice is near, the solitude is terrible! But how peacefully all things lie in the light..."
Reply With Quote
     
     
  #703  
Old Posted Feb 3, 2015, 1:06 AM
craner's Avatar
craner craner is offline
Go Tall or Go Home
 
Join Date: Mar 2007
Location: Calgary
Posts: 6,886
Quote:
Originally Posted by DizzyEdge View Post
Yeah I believe they only roughed in two stations, Bankers Hall and City Hall?
I recall Western Canadian Place (Husky) putting in provisions for a future underground LRT station when it was built.
Reply With Quote
     
     
  #704  
Old Posted Feb 3, 2015, 2:50 AM
Chadillaccc's Avatar
Chadillaccc Chadillaccc is offline
ARTchitecture
 
Join Date: Feb 2011
Location: Cala Ghearraidh
Posts: 22,842
Quote:
Originally Posted by Blue_Cypress View Post
Not a station, but certainly convertible spaces. I often times wish the 8th ave tunnel project would go ahead just so I could have the opportunity to work on it. I think we'd need an initiative like the Transportation Project Office again to make it a reality.

I've got drawings for the portion under city hall. Maybe I'll dig those up this eve.
That would be fantastic and I'm sure much appreciated if they are allowed to be posted here
__________________
Strong & Free

Mohkínstsis — 1.6 million people at the Foothills of the Rocky Mountains, 400 high-rises, a 300-metre SE to NW climb, over 1000 kilometres of pathways, with 20% of the urban area as parkland.
Reply With Quote
     
     
  #705  
Old Posted Feb 3, 2015, 3:59 PM
Barnes's Avatar
Barnes Barnes is offline
Registered User
 
Join Date: Nov 2006
Posts: 273
You can see the tunnel here:

Video Link
Reply With Quote
     
     
  #706  
Old Posted Feb 3, 2015, 7:17 PM
The Fisher Account's Avatar
The Fisher Account The Fisher Account is offline
Registered User
 
Join Date: Oct 2009
Location: Bridgeland - Calgary, AB
Posts: 1,023
This stupid underground City Hall/Bankers Hall station discussion comes up at least once every 6 months
Reply With Quote
     
     
  #707  
Old Posted Feb 3, 2015, 7:26 PM
Calgarian's Avatar
Calgarian Calgarian is offline
Registered User
 
Join Date: Jun 2006
Location: Calgary, AB
Posts: 24,161
Good thing that tunnel will sit empty for probably another 30 years...
__________________
Git'er done!
Reply With Quote
     
     
  #708  
Old Posted Feb 3, 2015, 8:04 PM
lineman's Avatar
lineman lineman is offline
power to the people!
 
Join Date: Oct 2008
Location: Crescent Heights, Calgary
Posts: 864
Quote:
Originally Posted by The Fisher Account View Post
This stupid underground City Hall/Bankers Hall station discussion comes up at least once every 6 months
I was thinking the same thing, but with Whole Foods.
Reply With Quote
     
     
  #709  
Old Posted Feb 3, 2015, 8:55 PM
UofC.engineer's Avatar
UofC.engineer UofC.engineer is offline
Laura Palmer
 
Join Date: Nov 2010
Location: Twin Peaks, Calgary, AB
Posts: 1,033
Quote:
Originally Posted by The Fisher Account View Post
This stupid underground City Hall/Bankers Hall station discussion comes up at least once every 6 months
Yup, I'll post something about it Aug. 3 2015 under the construction thread. I'll veil in causally with the hopes of derailing the thread.
Reply With Quote
     
     
  #710  
Old Posted Feb 3, 2015, 10:47 PM
H.E.Pennypacker's Avatar
H.E.Pennypacker H.E.Pennypacker is offline
Registered User
 
Join Date: May 2013
Posts: 1,941
So... Has excavation started on the NCL?? Chad you promised a picture

Really excited to see it get started
Reply With Quote
     
     
  #711  
Old Posted Feb 3, 2015, 10:56 PM
Spring2008 Spring2008 is offline
BANNED
 
Join Date: Apr 2008
Location: Lower Mount Royal, Calgary
Posts: 5,147
From the webcam

Looks like they've started, don't they still need to drill piles around the perimeter?



http://www.calgarymlc.ca/explore-pro...ruction-camera
Reply With Quote
     
     
  #712  
Old Posted Feb 3, 2015, 11:10 PM
You Need A Thneed's Avatar
You Need A Thneed You Need A Thneed is offline
Construction Enthusiast
 
Join Date: Feb 2007
Location: Castleridge, NE Calgary
Posts: 5,892
I don't think there is much underground to excavate for.
Reply With Quote
     
     
  #713  
Old Posted Feb 3, 2015, 11:16 PM
outoftheice outoftheice is offline
Registered User
 
Join Date: Jan 2009
Posts: 913
Quote:
Originally Posted by Spring2008 View Post
From the webcam

Looks like they've started, don't they still need to drill piles around the perimeter?
I believe the ditch we're seeing on the construction webcam is related to this "pipe ramming" project which has to do with placing some sort of piping underneath the LRT tracks without disturbing the tracks. The CMLC sent out a little email blurb about it last month but this is all I could find that mentions the project now:

http://www.evexperience.com/tunnelin...-site-pipe-ram

I think we're still a few months away before we see construction on the actual library building begin.
Reply With Quote
     
     
  #714  
Old Posted Feb 3, 2015, 11:20 PM
suburbia suburbia is offline
BANNED
 
Join Date: Mar 2012
Posts: 6,271
Quote:
Originally Posted by Spring2008 View Post
From the webcam

Looks like they've started, don't they still need to drill piles around the perimeter?



http://www.calgarymlc.ca/explore-pro...ruction-camera
I'm not liking how the NMC looks virtually integrated with the Salvation Army. I've noticed that from a variety of images / angles.
Reply With Quote
     
     
  #715  
Old Posted Feb 3, 2015, 11:23 PM
O-tacular's Avatar
O-tacular O-tacular is offline
Fake News
 
Join Date: Jul 2008
Location: Calgary
Posts: 24,187
Quote:
Originally Posted by outoftheice View Post
I believe the ditch we're seeing on the construction webcam is related to this "pipe ramming" project which has to do with placing some sort of piping underneath the LRT tracks without disturbing the tracks. The CMLC sent out a little email blurb about it last month but this is all I could find that mentions the project now:

http://www.evexperience.com/tunnelin...-site-pipe-ram

I think we're still a few months away before we see construction on the actual library building begin.
Reply With Quote
     
     
  #716  
Old Posted Feb 4, 2015, 4:55 AM
Chadillaccc's Avatar
Chadillaccc Chadillaccc is offline
ARTchitecture
 
Join Date: Feb 2011
Location: Cala Ghearraidh
Posts: 22,842
Sorry H.E.! Haven't had the chance to snap an update yet, but the pic Spring posted shows what I was talking about!
__________________
Strong & Free

Mohkínstsis — 1.6 million people at the Foothills of the Rocky Mountains, 400 high-rises, a 300-metre SE to NW climb, over 1000 kilometres of pathways, with 20% of the urban area as parkland.
Reply With Quote
     
     
  #717  
Old Posted Mar 6, 2015, 4:16 PM
Spring2008 Spring2008 is offline
BANNED
 
Join Date: Apr 2008
Location: Lower Mount Royal, Calgary
Posts: 5,147


Not much progress since last month.
Reply With Quote
     
     
  #718  
Old Posted Mar 6, 2015, 4:36 PM
speedog's Avatar
speedog speedog is offline
Moran supreme
 
Join Date: Sep 2010
Posts: 2,579
Kind of off track a bit, but as I drove by the existing main library last night I started wondering what will the city do with that building once the new library building is up and running. Anyone have any insider knowledge or hunches?
__________________
Just a wee bit below average prairie boy in Canada's third largest city and fourth largest CMA
Reply With Quote
     
     
  #719  
Old Posted Mar 6, 2015, 4:43 PM
The Fisher Account's Avatar
The Fisher Account The Fisher Account is offline
Registered User
 
Join Date: Oct 2009
Location: Bridgeland - Calgary, AB
Posts: 1,023
Quote:
Originally Posted by speedog View Post
Kind of off track a bit, but as I drove by the existing main library last night I started wondering what will the city do with that building once the new library building is up and running. Anyone have any insider knowledge or hunches?
Place is ripe to be demoed and redeveloped
Reply With Quote
     
     
  #720  
Old Posted Mar 6, 2015, 4:43 PM
Spring2008 Spring2008 is offline
BANNED
 
Join Date: Apr 2008
Location: Lower Mount Royal, Calgary
Posts: 5,147
Quote:
Originally Posted by speedog View Post
Kind of off track a bit, but as I drove by the existing main library last night I started wondering what will the city do with that building once the new library building is up and running. Anyone have any insider knowledge or hunches?
10 storey club. Euro style.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Calgary > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 4:11 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.