Quote:
Originally Posted by WarrenC12
When does it make sense to consolidate some of these OMCs? Especially as the line stretches out into cheaper land values.
As for opening, I'll be ecstatic if this project can remain on its current schedule. That's the best we can hope for.
|
There're 2 aspects to it: one is storage capacity to park and clean trains overnight, and one is space to do actual maintenance on the vehicles.
Currently, OMC 1 storage is at capacity, and it is the only site with maintenance capabilities.
OMC2 has no storage space, and limited maintenance capability (it's been used for repainting trains, but I don't know if it has maintenance pits and hoists). OMC2's parking lot has also been taken over for the new SkyTrain Control room.
OMC3 is essentially just storage space, and has already been expanded once to fit more trains.
OMC4 is meant to rival OMC1 in terms of providing both storage space and maintenance capabilities. This is important for the Broadway extension because otherwise any train with a problem needs to be limped all the way back around to Edmonds, which causes delays system-wide.
I don't think we know the exact scope of OMC5 yet, but I'm guessing it will be primarily for storage, with a bit of maintenance capacity.
The staging and positioning of trains going into service is also important, particularly given that maintenance staff are out along the track every night and trains can't move until they have all of their equipment back in the yard. New OMCs provide new staging areas for that maintenance equipment to deploy faster, and also allow trains to enter the line closer to where they need to go into revenue service.