HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates


Reply

 
Thread Tools Display Modes
     
     
  #41  
Old Posted Apr 21, 2022, 2:05 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
The 4th floor slabs are now installed. Setting up for the 4th floor concrete block wall builds.
Reply With Quote
     
     
  #42  
Old Posted Apr 21, 2022, 2:32 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
The Vomit Bag.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 45,896
It is so strange that they are not using cranes.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Reply With Quote
     
     
  #43  
Old Posted Apr 22, 2022, 12:58 AM
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,828
Quote:
Originally Posted by MolsonExport View Post
It is so strange that they are not using cranes.
This entire project has looked weird to me every time I drive by.
Reply With Quote
     
     
  #44  
Old Posted May 3, 2022, 6:17 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Making progress with building the 4th floor concrete block walls and the steel wall panels. Should be landing 5th floor concrete floor slabs in a couple of weeks.
Reply With Quote
     
     
  #45  
Old Posted Jun 1, 2022, 5:50 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Still no 5th floor slabs as they have not completed the 4th floor wall builds.
Reply With Quote
     
     
  #46  
Old Posted Jun 1, 2022, 6:25 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
The Vomit Bag.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 45,896
Has construction halted? Not much activity as of late.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Reply With Quote
     
     
  #47  
Old Posted Jun 1, 2022, 11:02 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Yes the trade union strike impacted this project too for 3 weeks



Quote:
Originally Posted by MolsonExport View Post
Has construction halted? Not much activity as of late.
Reply With Quote
     
     
  #48  
Old Posted Jun 19, 2022, 4:31 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
They have installed the 5th floor concrete slabs now and are starting on the 5th floor concrete block walls. No signs of structural steel for the 5th and 6th floors as of yet assuming they plan to continue using structural steel for the remaining floors.
Reply With Quote
     
     
  #49  
Old Posted Jun 28, 2022, 4:40 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
They have made good progress on building the 5th floor concrete block walls but still no signs of new structural steel for the next floors. They have installed some windows now on the ground floor level along Hyde Park Rd.
Reply With Quote
     
     
  #50  
Old Posted Jun 28, 2022, 9:03 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
The Vomit Bag.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 45,896
things have really slowed down on this site. Plus there is no evidence of excavation/construction on the northern half of this project.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell)
Reply With Quote
     
     
  #51  
Old Posted Jul 13, 2022, 2:10 AM
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 806
From the city's road construction map:



Set from July 18th to July 29th.
Reply With Quote
     
     
  #52  
Old Posted Jul 13, 2022, 1:02 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
I can't help but think if they had used a tower crane from the start that this 8s building would have already been topped out by now. Using form and pour method or even if they had done a poured lower level and gone with precast concrete they could have topped out this building by now. Still have 3 more floors plus a penthouse to build which at their pace will take them well into the Fall. To contrast this build with Tricar's 10s Northlink tower 2 building they built 2 levels of underground parking and 10 floors plus penthouse in less time then this building has done 1 level of underground and 5 floors. I wonder when they will demolition the plaza to the north and start phase 2. Hopefully they invest in using a tower crane for that phase.
Reply With Quote
     
     
  #53  
Old Posted Jul 18, 2022, 8:15 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
No mobile crane on site today. In fact no work appears to be happening today. They have installed some new structural steel for the 6th and 7th floors now.
Reply With Quote
     
     
  #54  
Old Posted Jul 22, 2022, 9:54 PM
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 4,828
Mobile crane was there today lifting concrete slabs.
Reply With Quote
     
     
  #55  
Old Posted Aug 4, 2022, 7:32 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
The 6th floor concrete block walls have started being built.
Reply With Quote
     
     
  #56  
Old Posted Aug 17, 2022, 2:34 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Have started installing the steel wall unit panels for the 6th floor. Should see the 7th floor concrete slabs being installed via mobile crane in a couple of weeks.


Great sunset photo from reddit


https://i.redd.it/3ezjg0p1c6i91.jpg
Reply With Quote
     
     
  #57  
Old Posted Aug 25, 2022, 8:02 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Mobile crane back on site installing the 7th floor concrete slabs on the west wing. Will likely continue next week with the Hyde Park Rd side followed by installing the structural steel for the 7th and 8th floor posts.
Reply With Quote
     
     
  #58  
Old Posted Sep 3, 2022, 3:05 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
The 7th floor slab is now installed and they have started on some of the 7th floor concrete block walls. No signs yet of structural steel for 7th and 8th floor posts.
Reply With Quote
     
     
  #59  
Old Posted Sep 21, 2022, 2:08 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Slowly building the 7th floor concrete block walls. This is a very slow build.
Reply With Quote
     
     
  #60  
Old Posted Oct 12, 2022, 7:20 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,151
Mobile crane back again to start installing the structural steel for the 7th and 8th floors.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 3:38 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.