Okay now for stuff:
Highrise Update:
Austonian: Working on its 52nd floor, almost to the next floor. 52nd floor ~50% complete. Crane at 676"
W Austin Hotel @ Residences: 9th floor in the works, workers trying to buff up construction speed. Cranes at 210"+ and 150"+
Ashton: Topped out, lobby work, currently leasing. Lighting has been activated.
Spring: Topped out, currently leasing. Lighting has been activated
Four Seasons Residences: Topped out, glass installation now up to 21/31 floors+Mechanical Penthouse. Crane at 420"+
It your last photo Mopacs, you can barely notice the W Austin Hotel & Residences poking up above the CSC buildings immediately left of the Hobbs building.
BTW, Legacy to me reminds me of a sore thumb sticking out of nowhere. Hotel Van Zandt might fix that a little.
In about a little more than half a month they are going to have to jump that crane for the Austonian.
Austonian Events:
June 30, 2009: The Austonian Becomes The Tallest Building In Austin. Me: "WOOT! This is tallest in Austin!"
July 21, 2009: Anticipated Structual Top Out/Floor 56 is complete. Me: "We only need that crown..."
September 12, 2009: Ballet Austin Fete'ish at the Austonian. Me: :-)
December 2009: Glass Crown is complete. Me: "All you need is housework people. Good job".