City and airport authority study possibilities for rail link
By David Reevely, OTTAWA CITIZEN July 8, 2013 1:06 PM
OTTAWA — The Ottawa airport authority and the city government are studying the best way to extend rail service to the Macdonald-Cartier International Airport.
The $227,000 study is to be finished in September and its results included in the city’s “transportation master plan,” the long-range vision for billions of dollars of road, rail, bus and cycling projects, said Jeff Byrne, the city’s chief procurement officer. The existence of the study, being carried out by transportation consulting firm Delcan, is revealed in a quarterly report on dozens of normally routine contracts let by senior city officials without running them past city council.
The city and the airport authority, which asked for the study, are splitting the cost, Byrne said. Delcan is the city’s favourite firm for rail planning, doing the primary work for both the first phase of rail, which is beginning construction now, and its western extension to Baseline station.
“It’s really sort of a high level study looking at aligning our planning effort with the city’s,” explained Michael Crockatt, the airport’s vice-president of business development. The airport is satisfied for now with its transit connection, the end of the line for the No. 97 Transitway bus, but its own long-range plan calls for the airport to become a hub of commerce and government employment and it’ll need better service for that to work.
Although the current O-Train line ends quite a bit farther north at Greenboro, the tracks it uses run right past the airport and beyond to south Gloucester. The city’s plans call for that line to be developed and, eventually, converted to the same electric light-rail technology it’s installing downtown.
The airport’s master plan includes a spur extending from the existing track to the terminal, though spurs that short can be difficult to integrate into regular rail service. One of the reasons the city rejects Carling Avenue as a route for a western extension of the first light-rail line is that it would leave Tunney’s Pasture hanging off by itself on the end of a spur, confusing riders about which trains end up where and how frequently. That’s likely the sort of problem that Delcan’s work is meant to resolve.
“We’ve always contemplated some sort of transit — rail transit — connection to the airport,” Crockatt said, though the study doesn’t prejudge anything. “It could be everything from different rail technologies to bus technology. We don’t know what the outcomes are going to be.”
Don’t get too excited about the prospect of taking a train to catch a flight soon, though. It took Toronto 20 years and eventually the promise of the Pan-Am Games to begin building a rail link from downtown to Pearson International Airport.
“I don’t think there’s going to be anything imminent that comes out of it,” Crockatt said.
[email protected]
ottawacitizen.com/greaterottawa
© Copyright (c) The Ottawa Citizen
http://www.ottawacitizen.com/news/City+a...ssibilities+rail+link/8630253/story.html