Quote:
Originally Posted by Bombardier
I wonder if the source was referring to the plant making the glass... now those guys could potentially work shifts 24/7 to make the glass panels, then just install on site as much as possible to not get shut down by the city. Will be interesting to see, no doubt.
|
Highly doubtful whether extra time will be added to the work day for the various reasons already stated, but this is a
big building and certainly could handle a number of installing crews. I've got no idea what it takes to put such crews together and what the logistics are in us say doubling the number of crews, issues like crane time for hoisting the units onto the correct floors for staging, etc. Even just off loading trucks at the site can be a task that has to be well planed and scheduled. These somewhat hidden details of high rise construction are fascinating.