Quote:
Originally Posted by Robag
Just out of curiousity, how many of the loading bridges are they able to use during the YXE construction?
|
Currently, there are 4 bridgeable gates plus 1+1 ground loading down from the 6 gates prior to construction; however, as phase 1 moves along and the charter season wraps up, SAA states gate congestion and inconvenience to passenger services will begin. I'm at an assumption that they will be removing gates A3/A5 leaving gates A1/A2 (Phase 2) as well as ground loading as the only available gates as Phase 1 construction includes the A3/A5 passenger/aircraft areas. As stated, this is an assumption as SAA has not notified us of any immediate changes but I suspect this will be the case within the next 4-5 weeks.