City planning staff is recommending that Council approve the zoning changes that would allow for the 8-storey building at the corner of Richmond St and University Dr.

This goes to the planning committee on June 11th and then to full council on June 25th.

https://london.ca/sites/default/files/20...nd%201163%20Richmond%20St%20%28CC%29.pdf
Reply With Quote
     
     
  #22  
Old Posted Jun 14, 2024, 2:55 AM
CanadianTalk's Avatar
CanadianTalk CanadianTalk is offline
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 1,284
Quote:
Originally Posted by CanadianTalk View Post
The province announced a new housing bill yesterday, and I found this part of it interesting...

Publicly assisted universities will be exempted from the Planning Act, the provincial rules that govern housing construction in Ontario. That means universities could push through projects without the need to request new zoning for the area or certain site plan requirements. ....

Global News article: https://globalnews.ca/news/10414592/ontario-housing-supply-updates/

Western officially submitted their zoning request for the Richmond site just last week, so I wonder if this exemption could actually apply here... and thus this zoning application would not need to continue.
And now we officially know that the exemption applies here. The bill received royal assent last week which means that zoning applications and site-plan applications are no longer required for universities that get provincial funding, which includes Western.

So now I would assume that they can directly proceed to the building permit filing stage.

Memo from city planning staff: https://pub-london.escribemeetings.com/filestream.ashx?DocumentId=109234

CTV article: https://london.ctvnews.ca/western-s-mass...m-municipal-planning-oversight-1.6926036
Reply With Quote
     
     
  #23  
Old Posted Jun 14, 2024, 10:40 AM
Djeffery's Avatar
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,192
So does that mean that now that Western owns the Harrison Pensa building at Talbot and Carling that they can knock that down, and build a 60 floor building if they want? If so, this sounds like universities might have found a new funding stream.
Reply With Quote
     
     
  #24  
Old Posted Jun 14, 2024, 4:43 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
Pass me the Vomit Bag.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 50,806
Alas, that downtown building has been on ice for quite some time, and will continue to be on ice for the foreseeable future, as it has moved (way) down the list of priorities for the university.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell). Sweet Loretta fart thought she was a cleaner, but she was a frying pan. (John Lennon)
Reply With Quote
     
     
  #25  
Old Posted Jun 14, 2024, 5:06 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Sadly it will probably still take city hall 6 months for all the various city dept to review and approve the building permit. Still not clear if this new Bill prevents OLT appeals from being filed. If not then it could take upwards of another 2 years to get thru the OLT processes.



Quote:
Originally Posted by CanadianTalk View Post
And now we officially know that the exemption applies here. The bill received royal assent last week which means that zoning applications and site-plan applications are no longer required for universities that get provincial funding, which includes Western.

So now I would assume that they can directly proceed to the building permit filing stage.

Memo from city planning staff: https://pub-london.escribemeetings.com/filestream.ashx?DocumentId=109234

CTV article: https://london.ctvnews.ca/western-s-mass...m-municipal-planning-oversight-1.6926036
Reply With Quote
     
     
  #26  
Old Posted Sep 16, 2024, 7:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Construction fencing has now gone up for the NW corner Richmond St entrance 8s residence building. Will be interesting to see who they hired as the general contractor builder of this building.
Reply With Quote
     
     
  #27  
Old Posted Nov 25, 2024, 7:25 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Looks like EllisDon has been awarded the contract to build the new 8s residence building at the Richmond gate. Excavator onsite and the digging has begun. Will be interesting to see if they centrally locate an extra long boom tower crane or go with a two tower cranes to cover the entire footprint.
Reply With Quote
     
     
  #28  
Old Posted Dec 11, 2024, 7:53 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
EllisDon has now set two tower crane bases for this future 8s building. Could see the cranes up before the holiday break.
Reply With Quote
     
     
  #29  
Old Posted Jan 9, 2025, 5:25 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Mobile crane at work today setting up the west side tower crane for this new residence. Would imagine they start on the east side tower crane soon after.

These will be the first 2 tower cranes of 2025 to go up.
Reply With Quote
     
     
  #30  
Old Posted Jan 10, 2025, 5:23 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
The west side tower crane is now standing. Excavator continues work on the east side of the building footprint pit.

looks like they are not putting up the east side tower crane but rather doing utility hookup prep.

https://london.ctvnews.ca/university-drive-at-western-university-closed-tuesday-1.7171319

Last edited by jammer139; Jan 14, 2025 at 3:54 PM.
Reply With Quote
     
     
  #31  
Old Posted Feb 4, 2025, 3:26 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Another road closure today for water main installation for this new building.

https://www.ctvnews.ca/london/article/university-drive-closed-for-watermain-installation/
Reply With Quote
     
     
  #32  
Old Posted Feb 23, 2025, 9:52 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
ED has now setup the 2nd tower crane on the east end of this building.

Last edited by jammer139; Mar 1, 2025 at 1:48 PM.
Reply With Quote
     
     
  #33  
Old Posted Mar 5, 2025, 3:21 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
They have now got some of the L1 walls poured on the west end of this building.
Reply With Quote
     
     
  #34  
Old Posted Apr 21, 2025, 2:37 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Working towards the east end of the building footprint on the L1 walls and posts of the foundation for this 8s residence building. Most of the building will not have a L1 level as it appears they will not offer underground parking.

Last edited by jammer139; Apr 21, 2025 at 11:52 PM.
Reply With Quote
     
     
  #35  
Old Posted Apr 27, 2025, 2:06 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
First ground floor walls and posts now poured on the west end of this building. Still working on the foundation footings and posts on the east end fronting Richmond St.
Reply With Quote
     
     
  #36  
Old Posted May 14, 2025, 12:45 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Starting to form for the 2nd floor slab on the west end while the last foundation footing walls and posts are being formed on the east end.
Reply With Quote
     
     
  #37  
Old Posted Jun 14, 2025, 6:55 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
They have now poured the 2nd floor slab on the west end and have got some of the 2nd floor wall forming started. The foundation wall footings and posts are all now poured on the east end.
Reply With Quote
     
     
  #38  
Old Posted Jul 8, 2025, 6:38 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Forming for the 3rd floor slab started on the west end. Have some of the 2nd floor walls and posts now poured in the middle section. Still have not poured the ground floor slab on the east end.
Reply With Quote
     
     
  #39  
Old Posted Jul 17, 2025, 7:24 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Still working on the east side ground floor. This end of the building has a larger footprint for the dinning/amenity spaces and some custom forming needs for the design elements.
Reply With Quote
     
     
  #40  
Old Posted Jul 29, 2025, 4:36 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,873
Have now poured the 3rd floor slab on the west end and have started forming the 3rd floor walls and posts. The center section is forming now for the 3rd floor slab and the east end has made some progress with ground floor walls and post although they still are working on the foundation footings for the extreme east end.

Last edited by jammer139; Jul 31, 2025 at 5:08 PM.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 4:31 AM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.