Quote:
Originally Posted by mitchellk12
yeah usually the boom takes a day to setup, then 1-2 for the crane itself. sometimes, theyll extend a day or 2 depending if its tied to the building since it takes time to dis-assemble that.
|
I am guessing too there is some slack time included to allow for winds as they won't do a lift if the wind gets over a certain defined speed.
Better to book the street closed for a few more days than may be needed and open it early than have to keep it closed longer than first thought.