http://westloop.org/news/contentview.asp?c=215898
UPDATE ON LAKE/MORGAN "L" STOP
* Funding source for project: local TIF money (100% active and healthy)
* Project Manager - Julian Silva
* Need for stop - gap between Clinton and Ashland stations
* Two entrance stations on NE/SE corners
* Bicycle racks on all four corners
* Customer assitance kiosks
* Concession venue
* 8 x 10 platforms
* 6-car canopy made of transluscent material
* Exterior in keeping with existing architecture (historic and contemporary)
- Perforated material to let in natural light
* Security and safety measures
- Security cameras monitored by CTA
- Lighting throughout station and surrounding sidewalks
* Station will be built entirely on the public way, using the existing parking lane as well as 7 ft. of sidewalk (sidewalk will be reduced from 15 ft. wide to 8 ft. wide)
* Possible traffic signal at corner
- Redirect trucks
* $34 million dollar project
- Cost is higher due to the lack of staging (streets and tracks will not be shut down during the length of construction)
- Value-engineered
* Bidding to be announced on CDOT website shortly
* Project timeline
- Construction documents: December 2008
- Advertisement: January 2009
- Notice to proceed: March 2009
- Projected completion: September 2010