Quote:
Originally Posted by VivaLFuego
^ most grade-separations would cost a great deal more than $10 million each (D/E + C) unless the local municipalities and IDOT would allow the roads being separated to be completely shut down during the project, which seems unlikely due to the lack of alternatives. If through vehicular traffic is to be maintained there is no way around each one being a very large project.
|
You probably know more about this than I do, but if you try to tunnel every road under the railroad, without adjusting the grade of the RR, all while maintaining both RR and vehicular traffic, of course it would get very expensive very quickly. That may nonetheless be the most cost effective option when you're building a grade separation for just a single road, but that approach doesn't scale at all, so it's not really what I'm talking about.
What I'm talking about is simply shutting down the railroad, and constructing an embankment on its existing alignment to raise it above the roads. No change to the roads themselves. This would apply only to areas with dense population and dense road networks.
Grades on a railroad should be maintained at 1% or so. Assume 23 feet vertical clearance (to allow for potential double-stacked container freight trains on the UP-NW), plus perhaps 6 feet for substructure, deck, and ballast. So that's 29 feet vertical rise, which would dictate an approach of 2900 feet on either side . Sure that's a lot of dirt to pile, but the kicker is that once you've built the approach and you're already got that 23 feet of clearance, you can cross as many streets as you want for much lower marginal cost. There are 5 grade crossings on the EJ&E in Barrington (4 roadway plus the UP-NW line) within a space of about 4000 feet, and way more than 2900 feet with no crossings on either side to allow for construction of the approaches. Same for West Chicago. 5 grade crossings within 2000 feet, and plenty of space on either side for the approaches. CN could knock all of those out, and shut up the nimbys, in one fell swoop.
Perhaps $10 million is an underestimate of the construction costs for a 2 mile long embankment (including approaches) but just pushing around and piling up some fill dirt really doesn't cost that much. With the railroad closed, construction of the embankment (fill, plus retaining walls where necessary) should be possible entirely within the RR right of way. Therefore the only time when the roads would have to be closed would be during the removal of the grade crossing, and during the installation of the bridge decks. The Main Street bridge replacement by CTA in Evanston showed that this can be done in a single weekend.
If the residents of Barrington choose to demand a trench instead of an embankment, which they may try to do, then all bets are off. Roadway closures, excavation issues, immense retaining walls, dealing with seepage and drainage, as well as crossings of water and sewer utilities would increase the costs of the project by a factor of 10 (and therefore into the realm of impossibility.)