Austin-Bergstrom International Airport
Excerpts from Master Plan & Current Capital Improvement Plan (CIP)
Current Conditions:
North Terminal-Barbara Jordan Terminal
-8.976 MAP
(2008)
-25 Gates
-24 Aerobridges
-45 Aircraft Stands
South Terminal
-0.063 MAP
(2008)
-2 Gates
-0 Aerobridges
-8 Aircraft Stands
______________________________________________________________
After Completion of CIP (Planning Level I Expansion) in August 2012:
North Terminal-Barbara Jordan Terminal
-33 Gates
-33 Aerobridges
-54 Aircraft Stands
South Terminal
-2 Gates
-0 Aerobridges
-8 Aircraft Stands
______________________________________________________________
After Completion of Planning Level II Expansion in ~2018 (Approved Plan A-07A):
North Terminal-Barbara Jordan Terminal
-33 Gates
-33 Aerobridges
-50 Aircraft Stands
New South Terminal
-10 Gates
-10 Aerobridges
-10 Aircraft Stands
______________________________________________________________
After Completion of Planning Level III Expansion in ~2024-2027 (Approved Plan A-07A):
North Terminal-Barbara Jordan Terminal
-33 Gates
-33 Aerobridges
-55 Aircraft Stands
New South Terminal
-22 Gates
-22 Aerobridges
-30 Aircraft Stands
______________________________________________________________
Ultimate Build Out – Beyond Planning Level III Expansion (Approved Plan A-07A):
North Terminal-Barbara Jordan Terminal
-33 Gates
-33 Aerobridges
-55 Aircraft Stands
New South Terminal
-22+ Gates
-22+ Aerobridges
-30+ Aircraft Stands
New Midfield Concourse “A”
-24+ Gates
-24+ Aerobridges
-24+ Aircraft Stands
New Midfield Concourse “B”
-24+ Gates
-24+ Aerobridges
-24+ Aircraft Stands
______________________________________________________________
The ball is already rolling on the planning and design for the CIP. It’s a $500 million project which is expected to be complete in August 2012.
Future expansion projects will be triggered by estimated demand and shall begin their respective planning, design and construction phases 5 years prior to reaching the trigger MAP.
Expansion Trigger Points (assumes ~4.11% annual growth beyond 2012):
-Planning Level I (Current CIP project) – 11 MAP
(estimated to reach this level in 2012).
-Planning Level II – 13.2 MAP
(estimated to reach this level in 2017-2018).
-Planning Level III – 18.4 MAP
(estimated to reach this level in 2027-2028).
Therefore, Expansion Planning, Design, and Construction Should Commence:
-Planning Level I (Current CIP project) – late 2008
-Planning Level II –
2012-2013
-Planning Level III –
2022-2023