Took me a long time to bike to the south side via Port Man Bridge (because taking SkyTrain would be too easy), but it was well worth it, since there was decent progress made on the south side.
Columbia Street is now open
Untitled by
Lexus LX 700, on Flickr
The is where future on ramp SB will be
Untitled by
Lexus LX 700, on Flickr
Untitled by
Lexus LX 700, on Flickr
They also added still girders connecting multiusepathway bridge t the rest of the pathway
Untitled by
Lexus LX 700, on Flickr
On the south side they made great progress. They removed about 10 old bridge spans, clearing the way for HWY 17 off ramp.
Untitled by
Lexus LX 700, on Flickr
This is where the missing girder will go to complete HWY 17 off-ramp, previously obstructed by old bridge
Untitled by
Lexus LX 700, on Flickr
This is where old bridge used to merge with the new one, now completely removed
Untitled by
Lexus LX 700, on Flickr
HWY 17 off-ramp - they poured some section with concrete already!
Untitled by
Lexus LX 700, on Flickr