DOMINO CONSTRUCTION UPDATE:Week of May 30th, 2016 and June 6th, 2016
Quote:
Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking. The public park located on Site C is open 6 days a week.
At Site E, superstructure concrete is underway and sections of the 8th floor slab on the south tower and supporting columns are being poured daily. All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work has begun.
|
DOMINO CONSTRUCTION UPDATE:Week of May 16th, 2016 and May 23rd, 2016
Quote:
Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking. The public park located on Site C is open 6 days a week.
At Site E, superstructure concrete is underway and sections of the 7th floor slab on the south tower and supporting columns are being poured daily. All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work has begun.
|
DOMINO CONSTRUCTION UPDATE:Week of May 2nd, 2016 and May 9th, 2016
Quote:
Hand demolition in The Refinery building is continuing. The removal of the bulkhead concrete decking on the river front is ongoing. New piers are being installed in the east river to support the future bulkhead decking. The public park located on Site C is open 6 days a week.
At Site E, superstructure concrete is underway and sections of the 6th floor slab on the south tower and supporting columns are being poured daily. All MEP trades are continuing deck work and coordination efforts. installation of CMU and horizontal MEP work has begun.
|
============================