Originally Posted by CastleScott
I think this plan is the best-go for the shorter more doable approach..
|
Yes, it would have been. But those locations are not where CHSR decided to build their first HSR tracks.
Most contractors, both public and private, start building what takes the longest to finish first. For CHSR,that would be the tunnels in the mountain passes. Yet CHSR decided to do them last.
Now we will have over $10 billion spent building a grade separated double track railroad corridor in the Valley, probably using for the near future the same rolling stock going at slightly higher max speeds that they do now. There are already two railroad corridors paralleling this brand new one.
If they had started building the tunnels first through let’s say the Grapevine, the existing Amtrak California trains could breach the Bakersfield to LA gap through these brand new tunnels. Now we have new tracks where they are not immediately useful instead.
It took WDOT two to three years to tunnel 2 miles under the Alaska Way Viaduct, how long do you think it would take CHSR to build at least one 20 mile tunnel? FYI, It took Switzerland 16 years to build a new 35 mile long tunnel recently.
Therefore, it should be safe to assume proceeding at 2 miles of tunneling per year. Yes, it will probably take 10 years to dig the new tunnels under and through the Grapevine. Why wait to do it last? It should have been done first!