New Austonian construction update. The date says 2/16 but I think it was just recently posted.
http://www.theaustonian.com/pics/2008-02-16_Austonian%20Report_22.pdf
Work activities completed thru the week ending February 16, 2008:
• Elevator shear walls poured at level B-1
• Concrete walls for garage ramp at B-1 poured
• Gravel backfill for slab of garage ramp installed and compacted
• Cast iron under slab rough-in 75% complete
• PVC under slab drainage pipe 75% compete
• Electrical rough-in in progress
• Waterproofing of below grade walls continues
• Pouring of concrete walls at B-1 continues
• Pouring of wall footings at south wall to start February 18, 2008
• Tower crane #1 “initial jump” to take place February 17, 2008. 5 sections to be added to tower (+/- 100’)
• Next critical milestone: pouring B-1 slab on grade scheduled for February 26, 2008