After a very rainy June, construction on site has benefited from sunny skies throughout July and into August. Our crews have been hard at work in the first two stages of the community and are on track to start work on the next stage of development in the coming weeks.
Work also continues on the Metro Line NW extension. Crews are making significant progress on the line from NAIT to Blatchford.
In August, crews are:
Continuing work on the trackway, pouring concrete and installing rails from Blatchford Gate Station working south.
Pouring the sidewalks, cycle tracks and crossings that will provide connections to the community once the LRT is complete.
Continuing interior and exterior work on the Blatchford and NAIT utility complexes, including the interior painting at the NAIT utility complex and roof installation at the Blatchford utility complex.
Installing the station shelters at both NAIT/Blatchford Market Station and Blatchford Gate Station. The station platforms are now completed with precast concrete panels in place."
https://blatchfordedmonton.ca/celebr...in-blatchford/