The new Humane society building now has the foundation footings all poured. They have back filled the foundation walls and appear to be grading and installing capped out utility services within the shell. Should see grading and prep soon with the ground floor slab poured in the coming weeks. Structural steel and ground floor concrete poured walls and concrete block soon after.
The LTC building at 1390 Dundas Street to the west has now started forming for the foundation footings. Still don't see this project page on the City's planning website but there is info about the permits on the permit site. The city websites are truly trash.