Historic restoration and infill, preserving the facades along Elmwood Avenue in the Elmwood Village neighborhood, adding new apartments
New construction and renovation/conversion of former metal fabrication company buildings in the the Rails (312 apartments) on Main Street, in the Lasalle neighborhood. Currently leasing with occupation beginning this month.
Final work underway (completing sky bridges and courtyard) in the conversion of former Trico Wiper factory into mixed use including 243 apartments. Leasing underway, with occupation this summer. Medical Center area.
Final work underway in the completion of Phase 1 of the Silo City conversion for former grain and milling facilities into mixed use including 158 apartments. Commercial offices are currently being occupied, with residential soon to follow. Along the Buffalo River.
Former Barcolounger factory complex (5 interconnected buildings) converted to mixed use campus including 119 apartments. Recently completed and occupied. Old First Ward neighborhood.
Former malt house conversion to mixed use with 80 apartments nearing completion, currently pre-leasing. Black Rock neighborhood.
Former Children's hospital complex conversion to mixed use including 136 apartments when completed. Currently in Phase 4/5, with final phase completion of tower conversion. Elmwood-Bryant neighborhood.
Noles Court and 1100 Michigan apartments (237 apartments) construction completed and now occupied. Medical Center area.
Pan-American Square with 160 apartments, under construction in North Buffalo neighborhood.
Main Street Lofts with 140 apartments and 7 townhomes now under construction on Main Street, Mid-Main area.
The Lawrence, 132 apartments, now under construction. Michigan Avenue, Medical Center area.
Work has begun on the Simon West conversion of existing office buildings and new construction to mixed use with 62 apartments.
Perry Homes, Phase 1, 405 apartments in multiple buildings, currently under construction in Old First Ward neighborhood.
Canalside Gateway, new visitor center and management office, under construction.
Ralph Wilson Centennial Park, former Lasalle Park, undergoing massive $150M+ redesign with shoreline redesign and protection work ongoing.
Not shown:
- interior work continues on the Statler Hotel conversion to 443 apartments and 200+ hotel rooms, although no schedule for completion has been given
- Eckhards Building conversion to 28 apartments and mixed use is expected to be completed this summer. Broadway-Fillmore.
- work has paused mid-construction on the Heritage Point apartments at Canalside, with no new updates since last reported still expecting 2025 completion
- work has paused mid construction on D'Youville Medical School building, with no updates on when work may resume.
- $50M rebuild of Main Street to include dedicated bike lanes is funded and scheduled to begin next year.
- $100M rebuild of Bailey Ave including BRT lanes is funded and scheduled to begin next year.
- permits have been opened to begin next phase of former Millard Fillmore hospital conversion to apartments, trailers on site, but no work yet begun.