I'll keep updating this as the meeting goes on.
-October 9th will have final plan to Airport Commission
Phase 1 Expansion 2027)
-21.7 Million Passengers, AO 287K, 48 Gates
-Future Terminal over the existing short term garage directly north of BJ Terminal
-Future island concourse but only about 20 gates. It'll be mostly symmetrical with a future western extension in the future. Catwalk from BJ terminal to new concourse will be about 80 feet high
-New Taxiway Delta
-New Terminal Curves
-New Airport Roadway Network
-New Central bag System
-New Apron, Taxiway and Taxilanes
-South Maintenance Ramp Rehab-Central Warehouse
-Consolidated Maintenance Facility
-New Support Facilities
-New Fuel Farm
-New Central Utility Plant
Phase 2 Expansion 2037)
-31.4 million passengers, AO 426K, Total Gates: 64
-Extend new island concourse and additional 12 gates west to match what we've seen in recent diagrams
Ultimate Expansion)
-Reroute 71 to expand airport footprint northward
-New Center Runway (Needed around 2045)
|