Originally Posted by J.OT13
Connaught Park
South of Carling Avenue, construction on the split-structure bridge continues with deck and parapet installation. The new Woodroffe Pedestrian Bridge construction continues through the fall with pier cap construction and
assembly of the steel structure; once it’s completed and opened to the public in Q2 2022 followed by removal of the current bridge.
Multi-use Pathway (MUP) construction to connect with the pedestrian bridge is underway, with paving anticipated in November.
In the area of Connaught Avenue, the drilling work is advancing well, with excavation and removals starting in October through December. Following excavation, formwork will be installed, and walls will be poured. Utilities relocation will also be ongoing through fall. Traffic will be maintained while performing drilling operations.

|
I was trying to place this view so I looked it up on Google Maps. It isn't quite the same perspective, but close. I'm sure the end justifies the means, but still, that is quite the mess.