October 10, 2019 Update
Greetings from our team at Oceanwide Center! Activities will continue 24 hours a day on the site as we prepare for our next major concrete foundation pour for the First Street tower. This concrete pour will start the evening of Friday October 11th at 10:00PM and end Saturday October 12th at approximately 1:00PM. Ecker Street between Jessie Street and Mission Street will be closed to traffic during this time.
On Sunday, October 13th we will be erecting an additional tower crane to support the construction of the First Street tower. No additional street closures are planned for this activity.