Quote:
Originally Posted by aberdeen5698 View Post
Safety. If there's some sort of emergency in one direction the wall prevents it from affecting both directions. Access doors at regular intervals allow the other half of the tunnel to be used for evacuation.
From Nov 27th document:

"Next Steps:

Dismantling the TBM
The tunnel boring machine will be dismantled and removed from the south tunnel work area. This will take about two months.

Tunnel Construction
Construction will occur in the tunnel to build the base for the track and the interior centre wall that separates inbound and outbound trains.

Track and Systems Installation
Once the interior base and centre wall are built, tunnel ventilation systems will be installed and then track installation will occur. Rails are welded outside the tunnel, and will be pushed from the north tunnel portal through the tunnel. Following track installation, power systems and communications systems will be installed."

Rails are welded together outside and pushed from the portal through the tunnel... I wonder what the longest section of rails that they will do this for is? And do they have to wait for the two months of TBM removal before advancing to the tunnel construction step, or can that be started sooner?
     
     
End
 
 
 

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 4:09 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.