It will be 15 years before the power station lot is developed, at least.
It requires city budgetary funding of a replacement station elsewhere, which is time added.
It requires then the planning, building, and integration of that new station, which is time added.
It requires a bidding process for selling that land, which is time added.
It requires the permit process, which is time added.
It requires then waiting for market fundamentals to necessitate building whatever was proposed and permitted (and to get the funding necessary), which is time added.
And then it requires actually building, which is another few years.
|