construction.tech.cornell.edu:
April 11 - April 25 Look Ahead
APRIL 11, 2014
Quote:
Work continues in buildings C, D, F, and H. Interior demolition has moved quickly through many floors and the abatement phase has begun in multiple buildings. There are also smaller, localized interior abatement projects underway in additional buildings at the Goldwater site.
Since the last construction update, the barge returned to remove debris. Given the interior demolition progress, barging trips will occur more frequently in the coming weeks. While Cornell continues to remove all demolition debris via barging, there are times when trucks with containers may be seen outside of the construction fence. Until one connector building is fully demolished, trucks must travel outside of the construction fence in order to get to the other side of the site. This issue will resolve itself as demolition gets further along. In addition, a small number of trucks should be expected because of the delivery and removal of materials, supplies, and small equipment.
The art conservation firms selected to remove and restore the WPA murals have mobilized on site. Testing of removal methodologies is underway on all three murals. We are on track for actual removal of the works of art later this month. After leaving Goldwater, the murals will undergo conservation work in the firms’ respective studios.
Available options for providing safe vehicular access to the South Point and Four Freedoms Parks continue to be studied by the engineering team.
|
|