I was talking to a fellow at the job site today and asked when they stop driving piles in and he said they stop when they get over 50 blows/foot. They'll come back later and cut the tops off the ones left sticking out. He also said they were half done with the pile driving. After all the piles are driven for the 2 towers, then they'll start driving piles for the podium. I told him to put a couple extra piles in Tower I.......
|