Salt Lake City & MSA/CSA Rundown


Downtown West - New Rocky Mountain Power Headquarters Project


Project Overview:

- Construction on Rocky Mountain Power's new headquarters and essential services campus in Salt Lake City is progressing on schedule, with foundation footings complete and structural steel framing actively rising toward a late-September top-out target.


- Current Construction Progress:
Foundations & Slabs: Most footings, foundation work, and ground-level concrete slab pours are finished.

- Steel Framing:
Structural steel components have arrived on site, and vertical assembly is moving fast. Milestone target construction teams expect the 10-story building's steel skeleton to top out by the end of September 2026

- Overview Location:
The new Power District master plan on Salt Lake City's west side near North Temple and the Jordan River.

- Size:
A 10-story, 300,000-square-foot, all-electric corporate headquarters and essential operational campus. Target Opening is scheduled to open in 2027 as the anchor project for the broader mixed-use district.



October 2025





July 30, 2026

Steel work continues to take shape on the Rocky Mountain Power office building in Salt Lake City. This 10-story structure includes substantial structural steel framing and complex seismic connection details designed to support the building's performance requirements.
Here you can see welding activities at one of the building's steel connections, where crews are installing and completing connection components within the structural frame. CMT is on-site providing quality control and quality assurance services associated with the structural steel construction and connection installation activities.
Once complete, the new office building will encompass approximately 300,000 square feet of gross floor area and rise 169 feet above the surrounding site. Located within The Power District on Salt Lake City's west side, the development occupies approximately 68,000 square feet and will serve as a prominent addition to the area near downtown, the airport, and the Jordan River.


Photo By CMT Technical Services @ Facebook



August 2, 2026



Photo By Snoogalator


.

Last edited by delts145; Sep 5, 2026 at 10:41 AM.
Reply With Quote
     
     
End
 
 
 

Go Back   SkyscraperPage Forum > Global Projects & Construction > City Compilations
Forum Jump



Forum Jump


All times are GMT. The time now is 3:56 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.