October 2008 Construction continues on schedule. The final Concrete slab is being poured for level 43 (mechanical floor). Curtain wall installation in the tower continues on levels 37, 38, 39 and 40 and is completed in the podium. Elevator installation continues in the high rise, mid rise and service elevator banks. Mechanical and electrical trades continue with their rough ins throughout the tower floors including lighting, fire alarm and sprinkler systems. Installation of access flooring in the typical office floor areas proceed up the building on levels 10, 11 and 12. Installation of access flooring in the podium will be completed to level 7. Finishes in the podium floor washrooms will be completed. Ground floor glazing will be complete as will the curtain wall for the feature stair. The ground floor lobby stone flooring will commence. The Ritz-Carlton will pour the 16, 17, and 18 floor slab and begin forming and pouring the 19th floor slab.
source:
http://rbccentre.ca/