309 Southdale Road West - Westmount Estates IV - 12s (Under Construction)

Excavation is now underway with HCM doing the foundation pilings. This is the 4th tower on the site. No artist rendering yet on their website but would expect it to be a clone of the 3rd building at 12 floors.


https://www.tricar.com/locations/westmount-estates-iv/
Reply With Quote
     
     
  #2  
Old Posted Dec 4, 2020, 4:55 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Looks like the pit will be deep enough for two levels of underground parking.
Reply With Quote
     
     
  #3  
Old Posted Feb 25, 2021, 5:23 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Tricar appears to have paused all work on the site. No progress since Dec. Must be focused on their Sunningdale condos.
Reply With Quote
     
     
  #4  
Old Posted Jun 22, 2022, 4:26 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Looks like Tricar has moved their tower crane from the recently topped out 15s on the Sarnia waterfront to this site.




https://www.tricar.com/locations/westmount-estates-iv/
Reply With Quote
     
     
  #5  
Old Posted Jun 26, 2022, 4:14 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Have poured some of the L2 perimeter walls in the SW corner of pit.
Reply With Quote
     
     
  #6  
Old Posted Jul 12, 2022, 5:12 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
They have been forming and pouring the footings along the south and east of pit perimeter. Will likely take the remainder of this year to built the 2 levels of underground parking for this building. Would expect they will use precast concrete for the above ground floors which should see this building topped out by end of 2023.
Reply With Quote
     
     
  #7  
Old Posted Jul 18, 2022, 8:06 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Tricar is using a blend of precast concrete walls and posts and formed and poured concrete for the L2 walls. Work progressing well in the south end of pit.
Reply With Quote
     
     
  #8  
Old Posted Aug 4, 2022, 7:06 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Have made alot of progress on the L2 walls and posts on the south end of the pit. Combination of poured and precast walls and posts. Working on prepping for the L2 floor slab pour at that end as well.
Reply With Quote
     
     
  #9  
Old Posted Aug 14, 2022, 7:37 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Have now got some of the L2 floor slab poured in the SW corner. Continuing with L2 walls and posts along the east side and working their way towards the north end of pit.
Reply With Quote
     
     
  #10  
Old Posted Aug 25, 2022, 7:50 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Have about 30% of the L1 concrete slabs installed on the south end. Making good progress with L2 walls and posts at the north end of the pit.
Reply With Quote
     
     
  #11  
Old Posted Sep 15, 2022, 3:45 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Walls being installed for the L1 level on the south side and have nearly finished the L1 floor slab installs on the north end.
Reply With Quote
     
     
  #12  
Old Posted Sep 28, 2022, 2:33 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
An older photo of site from Sept 6th showing L2 level progress. They are now well along with L1 level walls and posts and should be installing ground floor walls and posts in Nov.



https://www.facebook.com/photo/?fbid...00063640250782
Reply With Quote
     
     
  #13  
Old Posted Oct 7, 2022, 7:43 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Ground floor precast slabs now installed on the south end and also have some of the ground floor precast walls up. This is officially above ground now.
Reply With Quote
     
     
  #14  
Old Posted Oct 27, 2022, 1:27 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Ground floor precast walls are now installed and they have started landing the 2nd floor precast floor slabs on the south end. Given the floorplate size they will likely take 5 weeks to complete 2 floors using precast concrete walls, posts and floor slabs.
Reply With Quote
     
     
  #15  
Old Posted Nov 6, 2022, 7:50 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
The 2nd floor slab is now installed and they have about 60% of the 2nd floor walls and posts installed.
Reply With Quote
     
     
  #16  
Old Posted Nov 24, 2022, 5:21 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
They are really moving fast with 5th floor slabs being installed today on the south end of this project.
Reply With Quote
     
     
  #17  
Old Posted Dec 2, 2022, 6:27 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Have already started installing 6th floor walls. Progress is really fast with precast walls and floors.
Reply With Quote
     
     
  #18  
Old Posted Dec 21, 2022, 6:47 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Installation of the 7th floor walls on the south end nearly complete as they are nearly done the north end 6th floor walls. They have already started installing the window and balcony door units on the lower floors.
Reply With Quote
     
     
  #19  
Old Posted Jan 4, 2023, 10:51 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Have started installing the 8th floor precast concrete slabs on the south end.
Reply With Quote
     
     
  #20  
Old Posted Jan 13, 2023, 7:47 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 6,041
Have some of the 9th floor slabs now installed on the south end.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 2:44 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.