Hello everyone,
As has been suggested in the Southeast Transitway Thread, the latest federal funding announcement means that it is extremely likely the Green Line will proceed as LRT and not a transitway and will also be built in both north and south east regions of Calgary simultaneously. This thread has been created to discuss the project as it moves through the funding/planning and construction phases. With any luck we'll be using this thread to view opening day photos at some point in the early 2020s!!
Project Summary:
Green Line Map:
Green Line Flyover:
• Video Link
Green Line Stats:
- Will add 40 km of track to Calgary's existing 53 km LRT network
- 27 proposed stations
- 4 interchange stations with the proposed RouteAhead Rapid Transit Network (96th Ave N, 16th Ave N, 7th Ave S, Quarry Park)
- Low floor LRVs have been proposed as the preferred technology
- It is estimated almost 300,000k Calgarians live along the proposed route
- The route will serve 8 major employment centres in the city.
- Totally project cost estimated at $4.6 Billion
- Depending on additional funding, construction may begin as early as summer 2017
Green Line Advocacy:
Community advocacy has been a big factor in trying to secure funding for the Green Line. The LRT on the Green Foundation has played an instrumental role in this advocacy and is a good place to start for people who are interested in helping out to try and get this project built in its entirety. Their website can be found here:
http://www.lrtonthegreen.ca
Current Green Line Funding Status: (As of July 30, 2015)
Municipal: $52 million x 10 years for a total of $520 million
Provincial: None announced
Federal: Up to $1.53 billion from the newly created Public Transit Fund
Total Funding: $2.05 billion