Smile NEW YORK | Arthur Ashe Stadium Renovation

https://www.usta.com/en/home/stay-curren...um-headlines-us-open-transformation.html

Reimagined Arthur Ashe Stadium headlines historic US Open transformation





May 19, 2025


Quote:
The greatest stage in tennis is set for a grand makeover.

With the largest single investment in US Open history, the USTA will reimagine and modernize Arthur Ashe Stadium, create a new, state-of-the-art Player Performance Center and usher in a bold, visionary future for fans, players and partners.

The project, announced Monday, is an $800 million investment in the US Open and the USTA Billie Jean King National Tennis Center that is entirely self-funded by the USTA, with New York City continuing to benefit from more than $1.2 billion in annual economic impact due to the three weeks of the US Open.
Quote:
Combined with the US Open’s most recent transformation project, completed in 2018, the USTA has invested nearly $2 billion into the US Open and its home facility, without using any public, taxpayer or government funding.

The transformation will take shape over three phases and be completed by the 2027 US Open, without interrupting play or fan access for the 2025-26 events.

Quote:
Reimagined Arthur Ashe Stadium, Modernized and Enhanced at All Levels

The project will comprehensively enhance and modernize the US Open’s centerpiece, Arthur Ashe Stadium, elevating the experience for all fans inside tennis’ grandest stage. The enhancements include:

-A brand-new, visually striking Grand Entrance befitting the grandest stage in all of tennis.

-A 40-percent increase to the promenade-level concourse, adding significantly more open space for fans at the promenade and loge levels.

-Completely modernized concourses, with all-newly designed retail experiences and food and beverage spaces.

-Significantly increased access to restrooms on all concourses, and more escalators and elevators to all levels.

-An upward extension of the courtside-level bowl with 2,000 new seats, expanding the courtside experience from 3,000 to 5,000 seats.

-All-new club and restaurant areas, with enhanced dining options and premium hospitality spaces.

-Two new dedicated luxury suite levels.

-The spectator-facing elements of the Arthur Ashe Stadium reimagination will take place in advance of the 2026 and 2027 US Opens, with the full timeline specified later in this release.
Quote:
State-of-the-Art, $250-Million Player Performance Center to Provide Unparalleled Support

Close to 2,800 players and members of their teams converge on the US Open each year to put on one of the greatest shows in sports. This reimagination will build them a new, $250 million home that provides today’s and tomorrow’s top athletes best-in-class amenities, with both indoor and outdoor performance and relaxation spaces to give them everything they need to maximize their on-court performance.

The two-story, state-of-the-art facility will be built on the top two floors of a four-floor building on the west side of Arthur Ashe Stadium, adjacent to the practice courts. It will include:

-New and expanded indoor and outdoor fitness and warmup areas, featuring turf, track and US Open court surfaces for training.

-Redesigned and expansive locker rooms and lounges, providing players a spa-like experience.

-Upsized indoor player dining and an all-new outdoor player courtyard, as well as a new, dedicated cafe accessible only by players.

-Dedicated player entranceway, welcoming the best athletes on the planet to the biggest stage in tennis.

-The new Player Performance Center will be fully completed and accessible for players and teams by the 2027 US Open.
__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
Reply With Quote
     
     
  #2  
Old Posted May 22, 2025, 10:51 PM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 56,612
More...


Quote:
Phase 1 (in advance of the 2025 US Open)

-Structural work reinforcing the column load for Arthur Ashe Stadium, enabling for the in-stadium construction and overhaul to take place in future phases.

-The first two stories of the four-story building that will be the Player Performance Center in what is now Parking Lot A. The first two stories of the structure will contain parking.

-Mostly behind-the-scenes work, with no major changes noticeable to those attending the 2025 US Open.


Phase 2 (between the 2025-26 US Opens)

-The existing courtside and suite levels in Arthur Ashe Stadium will be removed and replaced with the new, expanded courtside bowl and the two new, dedicated luxury suite levels.

-The Player Performance Center—the top two floors of the four-floor facility in Parking Lot A—will be completed during this phase. While both levels of this facility will be constructed during this phase, it will not be finished and accessible to players until after Phase 3, as the interior will be completed during that time.


Phase 3 (between the 2026-27 US Opens)

The final projects in Arthur Ashe Stadium will be completed during this phase, including:

-The visionary Grand Entrance, designed by Daniel Libeskind.

-The new loge and promenade levels, including the new, expansive promenade concourse with an oversized, publicly accessible premium bar featuring expansive views of the Fountain Plaza and the Unisphere.

-Full enhancements to all concourses, including retail and food and beverage spaces, as well as restrooms and other amenities.

-Two new sets of escalators and two new elevator banks at the South entrance, improving fan traffic to all levels.

-The series of Garrett Singer-designed premium hospitality lounges in-stadium, enabling premium ticket holders the opportunity to access unparalleled hospitality without having to leave Arthur Ashe Stadium for the first time.

-The interior of the Player Performance Center will be completed during this phase and open to competitors and teams by the 2027 US Open.






__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
Reply With Quote
     
     
  #3  
Old Posted May 22, 2025, 10:56 PM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 56,612
Better look...







__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > General Development
Forum Jump



Forum Jump


All times are GMT. The time now is 12:43 AM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.