It's been a slow two weeks for any exciting news / updates. Just a few small things -
Kalamazoo -
Downtown Justice Facility - Current screen grab of the construction camera. Temporary weather protection is up on floors 1 & 2. Spray-on fireproofing is being applied to structural steel on these levels. You can see some exterior insulation & weatherproofing being applied at grade too. The block stair towers have risen a little since the previously-posted shot. On a vacant lot 2 blocks west (
here), I noticed a soil boring rig up and running last week. Not sure what that's about, but it appeared to be conducting some soil tests in that area. The lot is currently being used as construction staging for the justice center.

Source:
Sensera Systems
Two new infill houses are under construction on Wall Street - in the Vine neighborhood. One is a single-family home and the other is a duplex. These photos are from about a month ago -

Source:
LinkedIn | City of Kalamazoo
Richland Township -
Gull Lake Community School's new Performing Arts Center is complete -

Source:
LinkedIn | Kingscott Associates (Robert Atkins)
Battle Creek -
Based on the publish date of this article, I thought it might be a joke at first. But it looks legit -

Source:
Battle Creek Enquirer | Provided