Quote:
Originally Posted by BrutallyDishonest2 View Post
Blame the airport authority. They sabotaged the project and refused to fund widening the bridge over the storm channel.
Pedestrian signals are installed but not turned to a functional orientation since they re-did that intersection.

The councillor for the ward, Andrew Steven, predicted there would be a delay due to a change in the management. I think we can now say this is more than a simple delay.
__________________
Everything is real on this concrete and steel.