Description Architects: • NBBJ Sport • Agoos/Lovera Architects
Client: Philadelphia Eagles
Main Contractor: Joint venture Turner, Keating and McKissack
Acoustics Consultants: Acoustic Dimensions
Nova Centre Architect: Michael Graves and Associates
NovaCentre Engineers: Brinjac Engineering
NovaCentre Engineers: Brinjac Engineering
Cost: $320 million
Site Area: 43 acres
Stadium Width: 790ft
Stadium Length: 825ft
Pre-cast concrete: 4,000 pieces
Structural steel: 15,500t
Concrete: 58,500yd³
Field Size: 270ft x 424ft
Reinforcing steel: 7,200t
Steel Piles: 3,200
Pile foundations: 175,000 linear feet (33 miles)
Excavation: 100,000yd³
Seating: 66,000
Wheelchair accessible seats: 660
Club Seats: 9,000
Hospitality Suites: 163
Rolling doors: 18
Elevators: 12
Parking spaces: 22,000
Water pipes: Over 313,000 linear feet (over 59 miles)
Electrical Wiring: 5,250,000 linear feet (994 miles)
Hand Rails: 53,000 linear feet (10 miles)
Concession stands: 308
Site Preparation: April 2001
Excavation of North and South Stands: May 2001
Start of Pile Driving: May 2001
Start of Concrete Foundations: July 2001
Start of Main Concourse: July 2001
Start of Structural Work: September 2001
Top out west grandstand: May 2002
Top out east and south grandstand: July 2002
Top out east and south grandstand: July 2002
Seating Installation: August 2002
Build Playing Field: May 2003
Stadium Complete: August 2003