Has construction gone vertical yet? I haven't been past the site in a while.
Reply With Quote
     
     
  #142  
Old Posted Feb 1, 2023, 8:18 PM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,495
2/1/2023 Went by the site today. It appears to me that construction has stopped since November.
__________________
(Essex) Fox Plaza 52nd year resident in 2023 - (the building everyone loves to hate :------>))

Last edited by Jerry of San Fran; Feb 1, 2023 at 10:12 PM.
Reply With Quote
     
     
  #143  
Old Posted Feb 1, 2023, 9:05 PM
Zapatan's Avatar
Zapatan Zapatan is offline
DENNAB
 
Join Date: Aug 2009
Location: NA - Europe
Posts: 5,473
Quote:
Originally Posted by Jerry of San Fran View Post
2/1/2023 Went by the site today. It appears to me that construction as stopped since November.
Yikes, the one skyscraper U/C in San Francisco... hopefully it's temporary.

It's bad enough that none of the other projects in the pipeline seem to be moving forward either.
__________________
Dump Trump 2020
Reply With Quote
     
     
  #144  
Old Posted Feb 14, 2023, 8:52 PM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,495
UPDATE - I spoke to a Lend Lease employee at the job site today. She told me that work has not stopped. It has slowed for the next phase of work. The large blue crane has been moved from the Market St. side of the site to the north side to make way for work on the other half of the site. A San Francisco utility company will be doing work on the Fell St. side of the site in the near future. Good news that this wonderful building is moving along!
:------>))
__________________
(Essex) Fox Plaza 52nd year resident in 2023 - (the building everyone loves to hate :------>))
Reply With Quote
     
     
  #145  
Old Posted Feb 14, 2023, 10:37 PM
homebucket homebucket is online now
Registered User
 
Join Date: Jan 2012
Location: The Bay
Posts: 6,960
Quote:
Originally Posted by Jerry of San Fran View Post
UPDATE - I spoke to a Lend Lease employee at the job site today. She told me that work has not stopped. It has slowed for the next phase of work. The large blue crane has been moved from the Market St. side of the site to the north side to make way for work on the other half of the site. A San Francisco utility company will be doing work on the Fell St. side of the site in the near future. Good news that this wonderful building is moving along!
:------>))
Whew... what a relief!
Reply With Quote
     
     
  #146  
Old Posted Feb 15, 2023, 1:09 AM
Charmy2 Charmy2 is online now
Registered User
 
Join Date: Jan 2022
Location: San Francisco
Posts: 29
Awesome! Fingers crossed we see it going vertical by July!
Reply With Quote
     
     
  #147  
Old Posted Feb 18, 2023, 9:37 PM
memester memester is offline
Registered User
 
Join Date: May 2020
Posts: 49
Quote:
Originally Posted by Charmy2 View Post
Awesome! Fingers crossed we see it going vertical by July!
Excavation and caisson construction could take up to 12 months. It can't go vertical until that work is complete.
Reply With Quote
     
     
  #148  
Old Posted Feb 28, 2023, 3:22 AM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,495
2/27/2023 - The San Francisco Gate says that "...pausing due to permit issues related to its proximity to BART." "...recent heavy rains for the delay in progress."
"Site activity will become more intense shortly," Arden Hearing, executive general manager of West Coast development for Lendlease."
BART spokesperson confirmed to the Business Times that “the pause is the result of adjustments’ the transit agency requested due to the project's proximity to underground rail tunnels.”
The whole story can be read at: https://www.sfgate.com/
__________________
(Essex) Fox Plaza 52nd year resident in 2023 - (the building everyone loves to hate :------>))
Reply With Quote
     
     
  #149  
Old Posted Mar 9, 2023, 1:49 PM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,495
3/08/2023 - WORK HAS RESUMED. WITH RAIN FORECAST THERE WILL BE A SLOWDOWN IN THE NEXT TWO WEEKS. I TOOK THIS PHOTO FROM MARKET STREET.

30 Van Ness Avenue, San Francisco
__________________
(Essex) Fox Plaza 52nd year resident in 2023 - (the building everyone loves to hate :------>))
Reply With Quote
     
     
  #150  
Old Posted Mar 17, 2023, 9:04 PM
Charmy2 Charmy2 is online now
Registered User
 
Join Date: Jan 2022
Location: San Francisco
Posts: 29
So is it like on hold officially now? I heard its having issues with permits surrounding the nearby BART line also we've been having this awful weather. If so that would be super unfortunate to see, SF's only skyscraper under construction put on hold. Still waiting on Oceanwide to continue and for Parcel F to begin...
Reply With Quote
     
     
  #151  
Old Posted Mar 18, 2023, 8:07 PM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,495
Quote:
Originally Posted by Charmy2 View Post
So is it like on hold officially now? I heard its having issues with permits surrounding the nearby BART line also we've been having this awful weather. If so that would be super unfortunate to see, SF's only skyscraper under construction put on hold. Still waiting on Oceanwide to continue and for Parcel F to begin...
3/18/2023 as mentioned in my last post, work has resumed. I have been by the site twice in the last week and there is a huge amount of work happening now on the south end of the foundation. 30 Van Ness if moving along nicely!
__________________
(Essex) Fox Plaza 52nd year resident in 2023 - (the building everyone loves to hate :------>))
Reply With Quote
     
     
  #152  
Old Posted Mar 19, 2023, 6:12 PM
Charmy2 Charmy2 is online now
Registered User
 
Join Date: Jan 2022
Location: San Francisco
Posts: 29
Quote:
Originally Posted by Jerry of San Fran View Post
3/18/2023 as mentioned in my last post, work has resumed. I have been by the site twice in the last week and there is a huge amount of work happening now on the south end of the foundation. 30 Van Ness if moving along nicely!
Awesome. Thanks for the update!
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > Skyscraper & Highrise Construction
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 12:17 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2023, vBulletin Solutions, Inc.