Quote:
Originally Posted by The ATX
... and the Domain III & Domain IV site plans were approved and released.
|
Bowen - Application Date: Oct 18,2018, Approved Oct 11, 2019 - 12 months
Tower II - Application Date: Oct 18, 2018, Approved Sep 6 2019 - 11 months
Tower III - Application Date: Oct 18 2018, Approved Oct 9th 2020 - 24 months
Tower IV - Application Date: Jan 17, 2019, Approved Oct 9th, 2020 - 21 months
If I remember correctly there was an issue with the drainage pond. It was too small for the development so the developer had to make changes to expand the pond and that took extra time because the pond had a different owner. Looks like that was all approved finally and they can get started. They already filed an EV plan for both sites. So looks like they are going to build them now after all regardless of WFH.