Old Posted Aug 1, 2022, 4:02 PM
Maldive's Avatar
Maldive Maldive is offline
Registered User
 
Join Date: Sep 2004
Posts: 2,356
Quote:
Originally Posted by colemonkee View Post
Looks like they're starting the slow march upwards with the corner plates, but they no longer appear to be cantilevered. Are those corner columns steel or concrete? I ask because I don't see any column form work.
As I noted above, once the forms move up, the next set of hangers for 3 more floors will be installed, to be followed by concrete pours for the missing corner pieces that you see in the photo (each set of floors have cantilever support from the angled hangers).

If you look at the photo I posted, you'll note that corner columns are for the two floors only (they are reinforced concrete btw), while the third floor may not require a corner column*... its ceiling is the 4th floor slab which will hang from the bottom of the next set of hangers*.

*Don't see any corner column forms for the third floor .. so that's my theory ;-).
__________________
circa 2008: home of the 3rd best skyline in N.A. +++ circa 2028: home of the 2nd best skyline in N.A.

Last edited by Maldive; Aug 1, 2022 at 4:18 PM.
Reply With Quote
     
     
  #602  
Old Posted Aug 1, 2022, 5:58 PM
Gresto's Avatar
Gresto Gresto is offline
Registered User
 
Join Date: Jul 2009
Location: Toronto
Posts: 2,829
Quote:
Originally Posted by Maldive View Post
If Sam get his height increase... this will be a 9+ on completion (hope I'm around to see it).
You're right, the height increase is vital because then the top section will be symmetrical with the others. I don't understand why the city would refuse such a minor increase, but curiouser things have happened.
For any of us to be around to see the finished product, these guys will have to pick up the pace.
Reply With Quote
     
     
  #603  
Old Posted Aug 5, 2022, 9:00 PM
Maldive's Avatar
Maldive Maldive is offline
Registered User
 
Join Date: Sep 2004
Posts: 2,356
The One | 338.3m | 94s | Mizrahi Developments | Foster + Partners l u/c

This thing is breaking the sound barrier now (compared to a few months/years ago ;-).

thaivic

Walls poured and forms for the next floor slab underway.

Benito

Benito

Forming up some more (missing) corners. At some point I knew why the corners, supported by the hangers, were left until later to be poured... but now I've totally forgotten.

Benito
__________________
circa 2008: home of the 3rd best skyline in N.A. +++ circa 2028: home of the 2nd best skyline in N.A.
Reply With Quote
     
     
  #604  
Old Posted Aug 10, 2022, 3:15 PM
Maldive's Avatar
Maldive Maldive is offline
Registered User
 
Join Date: Sep 2004
Posts: 2,356
The One | 338.3m | 94s | Mizrahi Developments | Foster + Partners l u/c

Walls and columns were poured last Wednesday evening, and today (Wednesday) they are pouring the the next floor … never seen that accomplished here in one week.

They have also placed the rebar cages for the next mega-columns and inner core (elevators). Gob-smacked lol.


Benito

Benito
__________________
circa 2008: home of the 3rd best skyline in N.A. +++ circa 2028: home of the 2nd best skyline in N.A.
Reply With Quote
     
     
  #605  
Old Posted Aug 11, 2022, 9:03 PM
GeneralLeeTPHLS's Avatar
GeneralLeeTPHLS GeneralLeeTPHLS is offline
Midtowner since 2K
 
Join Date: Aug 2015
Location: Midtown Toronto
Posts: 4,409
__________________
"Living life on the edge"
Reply With Quote
     
     
  #606  
Old Posted Aug 14, 2022, 2:48 PM
Maldive's Avatar
Maldive Maldive is offline
Registered User
 
Join Date: Sep 2004
Posts: 2,356
The One | 338.3m | 94s | Mizrahi Developments | Foster + Partners l u/c

Ready for another big concrete pour for walls and super-columns… just 5 days after the floor slab was poured… not bad ;-).


Benito

The crane in the centre of the photo. If Sam Mizrahi gets his height increase to 94 storeys, The One will rise taller than the top of the frame in the photo below (almost pencil tower status ;-).

The tallest on the right is One Bloor East @ 257 metres… so The One would be more than 81 metres taller, just across the street.


j_yyz

Johnny Au

The One will appear just left of centre in this shot of the growing Yonge Street canyon.

wmedia
__________________
circa 2008: home of the 3rd best skyline in N.A. +++ circa 2028: home of the 2nd best skyline in N.A.

Last edited by Maldive; Aug 15, 2022 at 10:41 PM.
Reply With Quote
     
     
  #607  
Old Posted Aug 15, 2022, 10:26 PM
Maldive's Avatar
Maldive Maldive is offline
Registered User
 
Join Date: Sep 2004
Posts: 2,356
The One | 338.3m | 94s | Mizrahi Developments | Foster + Partners

When it’s sunny... it still pours.

How about a week between pouring a floor slab and then pouring the walls and super-columns?? What parallel universe are we living in?


Benito
__________________
circa 2008: home of the 3rd best skyline in N.A. +++ circa 2028: home of the 2nd best skyline in N.A.

Last edited by Maldive; Yesterday at 1:13 AM.
Reply With Quote
     
     
  #608  
Old Posted Today, 4:44 AM
rivernorthlurker rivernorthlurker is offline
Registered User
 
Join Date: Dec 2018
Location: Chicago
Posts: 939
Literally the slowest construction of a building I've ever seen that hasn't fully stopped construction (though I know this has a couple times).

Quote:
Originally Posted by Maldive View Post
The One | 338.3m | 94s | Mizrahi Developments | Foster + Partners

When it’s sunny... it still pours.

How about a week between pouring a floor slab and then pouring the walls and super-columns?? What parallel universe are we living in?


Benito
Reply With Quote
     
     
  #609  
Old Posted Today, 2:54 PM
Maldive's Avatar
Maldive Maldive is offline
Registered User
 
Join Date: Sep 2004
Posts: 2,356
^ Old news but thanks for trolling (welcome to the ignore list, they're a fun bunch).

The point of my post (if you read it)... is obviously that pouring a floor slab and then the walls and super-columns in just one week (instead of a month or two months or...) is pretty good evidence that times have finally changed (thanks to skybuild elevators and new forming).

P.S.

Already forming up the next floor today.

Benito
__________________
circa 2008: home of the 3rd best skyline in N.A. +++ circa 2028: home of the 2nd best skyline in N.A.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > Supertall Construction
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 10:15 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2022, vBulletin Solutions, Inc.