HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates


Reply

 
Thread Tools Display Modes
     
     
  #1  
Old Posted Sep 19, 2019, 4:42 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Centro by Old Oak - 40s, 29s, 10s (Under Construction)

Given the apparent start of this major project now that Old Oak has purchased it from Rygar. Its time to start a new thread to track the progress of the construction. And put to rest the out-dated thread.

Heavy equipment for the pilings is now on site. They will be there for quite some time if they in fact plan to excavate for 5 levels of underground parking. The foundation for these towers will need to go down very deep.
Reply With Quote
     
     
  #2  
Old Posted Sep 26, 2019, 4:37 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Pile driver for steel girders and piling auger on site now. Looks like they are starting along Talbot St side. Digging the 5 floor pit excavation for these 3 towers will take well into 2020. Foundation work and footings will likely mean spring before they get to ground level.
Reply With Quote
     
     
  #3  
Old Posted Sep 27, 2019, 5:00 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Wonder who Old Oak sub contracted the foundation work to? The 515 Richmond tower should be topped out by the time they have dug out the foundation. Will Ellis-Don get the contract for the construction? And move their crew over to Centro towers project? The timing would work out I suspect.
Reply With Quote
     
     
  #4  
Old Posted Sep 28, 2019, 3:02 AM
ldoto's Avatar
ldoto ldoto is offline
Londoner
 
Join Date: Jan 2004
Location: London,Ont
Posts: 1,322
I can’t wait to see this one!!!!
Reply With Quote
     
     
  #5  
Old Posted Sep 29, 2019, 5:26 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Have just started with the caisson auger pilings on west side. Looks like HCM Group is the foundation contractor for this. http://www.hcgroup.ca/

Reply With Quote
     
     
  #6  
Old Posted Sep 30, 2019, 3:40 PM
BIGGUY2891 BIGGUY2891 is offline
Registered User
 
Join Date: Nov 2010
Location: London
Posts: 41

Last edited by BIGGUY2891; Sep 30, 2019 at 3:59 PM.
Reply With Quote
     
     
  #7  
Old Posted Oct 4, 2019, 11:37 AM
Innsertnamehere's Avatar
Innsertnamehere Innsertnamehere is offline
Registered User
 
Join Date: Jan 2010
Location: Hamilton
Posts: 11,595
Quote:
Originally Posted by BIGGUY2891 View Post
Use imgur.com to upload then copy the image URL and use the little photo button in the posting window on this website.
Reply With Quote
     
     
  #8  
Old Posted Oct 6, 2019, 12:06 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Still not clear what the plans for the 2 storey house that was the lawyer's offices are. Is it going to be taken down? Or somehow undercut to excavate the parking levels below it? Rygar was planning to incorporate the house into podium of the 29s tower. The extra cost of doing that may be dropped by Old Oak I suspect.
Reply With Quote
     
     
  #9  
Old Posted Oct 6, 2019, 5:32 PM
ssiguy ssiguy is offline
Registered User
 
Join Date: Mar 2006
Location: White Rock BC
Posts: 10,731
This is great news for the city and helps to continually fill in the empty lots downtown.
Reply With Quote
     
     
  #10  
Old Posted Oct 6, 2019, 10:34 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,455
Probably should have a pic of the project in this thread.



And this is not just good news, it's a new tallest for London and a pretty nice looking building.
Reply With Quote
     
     
  #11  
Old Posted Oct 7, 2019, 4:06 AM
ldoto's Avatar
ldoto ldoto is offline
Londoner
 
Join Date: Jan 2004
Location: London,Ont
Posts: 1,322
"it's a new tallest for London"

yep!!!
Reply With Quote
     
     
  #12  
Old Posted Oct 7, 2019, 1:00 PM
FWD15 FWD15 is offline
Registered User
 
Join Date: Jan 2017
Location: London
Posts: 43
Does anyone know if Old Oak is going to build it in phases as was originally proposed? I believe originally the low rise centre was going to be built first and then the tallest tower second with the third tower being added at a later date. I think the delay with the third tower was originally due to lease issues with the lawyers office that was to be incorporated into the base of that tower.
Reply With Quote
     
     
  #13  
Old Posted Oct 7, 2019, 3:03 PM
BIGGUY2891 BIGGUY2891 is offline
Registered User
 
Join Date: Nov 2010
Location: London
Posts: 41
Quote:
Originally Posted by FWD15 View Post
Does anyone know if Old Oak is going to build it in phases as was originally proposed? I believe originally the low rise centre was going to be built first and then the tallest tower second with the third tower being added at a later date. I think the delay with the third tower was originally due to lease issues with the lawyers office that was to be incorporated into the base of that tower.
Seems likely they're doing it all at once. Old Oak's president said he wants it done by 2021; "Old Oak will start excavating the site, digging down six metres to clean out soil where a gas station once stood, in July. Bierbaum hopes to have the project completed in 2021." Their website states occupancy will be ready by 2022.
Reply With Quote
     
     
  #14  
Old Posted Oct 7, 2019, 6:56 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,455
Old Oak is pretty active on Facebook and they answered someone who asked if they will have 2 cranes going at once - the answer was yes they will be building with two cranes.
Reply With Quote
     
     
  #15  
Old Posted Oct 8, 2019, 1:10 PM
FWD15 FWD15 is offline
Registered User
 
Join Date: Jan 2017
Location: London
Posts: 43
Quote:
Originally Posted by BIGGUY2891 View Post
Seems likely they're doing it all at once. Old Oak's president said he wants it done by 2021; "Old Oak will start excavating the site, digging down six metres to clean out soil where a gas station once stood, in July. Bierbaum hopes to have the project completed in 2021." Their website states occupancy will be ready by 2022.
Good to hear. I was always worried that phase 1 would get built and the rest would never develop. Looking forward to seeing it all take shape.
Reply With Quote
     
     
  #16  
Old Posted Oct 9, 2019, 2:51 AM
inimrepus inimrepus is offline
Registered User
 
Join Date: Jan 2017
Location: Earth
Posts: 142
What's the address of this build? Am I missing it somewhere?
Reply With Quote
     
     
  #17  
Old Posted Oct 9, 2019, 3:48 AM
BIGGUY2891 BIGGUY2891 is offline
Registered User
 
Join Date: Nov 2010
Location: London
Posts: 41
Quote:
Originally Posted by inimrepus View Post
What's the address of this build? Am I missing it somewhere?
Seems to still be referenced by multiple addresses and the city database doesn't show the properties as merged yet. 100 Fullarton Street, 475-501 Talbot Street and 93 & 95 Dufferin Avenue
Reply With Quote
     
     
  #18  
Old Posted Oct 10, 2019, 6:58 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Drilling and concrete filling of the caisson pilings continues. Expect this to go on for many weeks to come. The pedestrian walkway covers were being installed along Dufferin and Talbot st today.
Reply With Quote
     
     
  #19  
Old Posted Oct 16, 2019, 10:25 PM
greenday99 greenday99 is offline
sketchy dude
 
Join Date: Oct 2019
Location: london
Posts: 63
it is 100 fullarton
Reply With Quote
     
     
  #20  
Old Posted Oct 16, 2019, 10:30 PM
greenday99 greenday99 is offline
sketchy dude
 
Join Date: Oct 2019
Location: london
Posts: 63
what is the height of all these building's? anyone know?
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 10:31 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.