1st floor walls now started on north end of building as they wrap up the L1 level on south side.
Reply With Quote
     
     
  #22  
Old Posted Jul 15, 2020, 3:33 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Almost done the 1st floor walls. Have started excavating the underground level for the next tower. The first 2 floors are podium base.
Reply With Quote
     
     
  #23  
Old Posted Jul 21, 2020, 8:06 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Installing the 2nd floor concrete slabs on the north end of the 1st building now. The podium base is 2 floors with floors 3-9 being the main tower with a setback 10th floor as a penthouse level with larger patios. Digging continues for underground level for tower 2 along Sunningdale Rd and the new roadway to serve the 4 buildings is being prepared.
Reply With Quote
     
     
  #24  
Old Posted Jul 23, 2020, 7:00 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Some of the 2nd floor walls now installed.
Reply With Quote
     
     
  #25  
Old Posted Aug 8, 2020, 5:00 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
2nd floor walls are now installed. 3rd floor slabs should be well underway by next week. Floors 3 thru 9 are the main tower which sits on the 2 floor podium base.
Reply With Quote
     
     
  #26  
Old Posted Aug 14, 2020, 2:16 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Wrapping up the 3rd floor slab installation. The pit for tower 2 is dug and they have the mobile crane there. Suspect they will be digging the footing foundations soon as the towers will share the two level underground parking garage.
Reply With Quote
     
     
  #27  
Old Posted Aug 18, 2020, 12:52 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
3rd floor walls now started. Still have some of the 3rd floor slabs to install on south side of building one.
Reply With Quote
     
     
  #28  
Old Posted Aug 21, 2020, 2:24 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
3rd floor slabs now finished. 3rd floor walls continuing.
Reply With Quote
     
     
  #29  
Old Posted Sep 2, 2020, 8:26 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Have started on some of the 4th floor walls and also have the north side 4th floor slabs installed.
Reply With Quote
     
     
  #30  
Old Posted Sep 12, 2020, 3:23 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Most of the 4th floor walls are now installed. Should see 5th floor slab installation started next week. Pace is around 2 floors every 5 weeks, so should see the 10th floor completed in 15 weeks.
Reply With Quote
     
     
  #31  
Old Posted Sep 17, 2020, 11:17 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
5th floor slab installation has started on the north end of the building.
Reply With Quote
     
     
  #32  
Old Posted Sep 22, 2020, 11:38 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
5th floor slab is now done and 70% of the 5th floor walls are now installed. Window installation has started on 1st floor. Work continues in the pit for tower 2 footings and the continuation of the underground garage below tower 2.
Reply With Quote
     
     
  #33  
Old Posted Sep 28, 2020, 6:17 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Have nearly 50% of the sixth floor slabs installed now as they wrap up the 5th floor walls on south end. Excavation for parking under tower 2 is complete and they appear to be prepping to start foundation footings. Would be smart to get them dug and poured before the cold weather sets in.
Reply With Quote
     
     
  #34  
Old Posted Sep 30, 2020, 5:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Have some of the 6th floor walls installed on north side. Should be completing the 6th floor slabs on the south side of tower one soon.
Reply With Quote
     
     
  #35  
Old Posted Oct 2, 2020, 5:06 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
6th floor slab installs nearly finished. Most of the north end 6th floor walls are also installed now.
Reply With Quote
     
     
  #36  
Old Posted Oct 14, 2020, 2:56 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Some of the 7th floor slabs installed now on north side of tower
Reply With Quote
     
     
  #37  
Old Posted Oct 16, 2020, 3:43 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
About half of 7th floor slab is now installed and even have some of the 7th floor wall panels installed.
Reply With Quote
     
     
  #38  
Old Posted Oct 18, 2020, 4:21 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Footings now poured for tower 2 and forming started for L2 level walls for garage.
Reply With Quote
     
     
  #39  
Old Posted Nov 1, 2020, 1:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
Wrapping up the 7th floor walls and have some of the 8th floor slabs now installed. Preparing of foundation slab for tower 2 continues.
Reply With Quote
     
     
  #40  
Old Posted Nov 5, 2020, 5:59 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,776
8th floor walls well under way now on north end of building.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 11:56 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.