  #61  
Old Posted Jun 28, 2019, 9:39 PM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Where the lights are much brighter
Posts: 12,045
It looks like the groundbreaking was pushed out three or four months. A permit for right-of-way closures for construction indicates that this will start at the end of October.

https://abc.austintexas.gov/web/perm...rtyrsn=2017935
__________________
Follow The ATX on X:
https://twitter.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
     
  #62  
Old Posted Jul 26, 2019, 1:26 AM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Where the lights are much brighter
Posts: 12,045
This project is good to go. But has anyone noticed if site prep has started? There were a bunch of construction related permits filed today.
__________________
Follow The ATX on X:
https://twitter.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
     
  #63  
Old Posted Jul 26, 2019, 4:21 AM
MichaelB MichaelB is online now
Registered User
 
Join Date: May 2006
Location: North edge of Downtown
Posts: 3,208
Quote:
Originally Posted by The ATX View Post
This project is good to go. But has anyone noticed if site prep has started? There were a bunch of construction related permits filed today.
Nothing yet.
Reply With Quote
     
     
  #64  
Old Posted Aug 22, 2019, 8:06 PM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Where the lights are much brighter
Posts: 12,045
Five more permits were filed today related to utilities and excavation. So this one has to be starting soon.
__________________
Follow The ATX on X:
https://twitter.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
     
  #65  
Old Posted Sep 11, 2019, 5:43 PM
MBAus MBAus is offline
Registered User
 
Join Date: Apr 2019
Posts: 35
Noticed the other day this parking lot is blocked off. Looks like they are getting ready to dig.
Reply With Quote
     
     
  #66  
Old Posted Sep 16, 2019, 12:12 AM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Where the lights are much brighter
Posts: 12,045
Here's a photo from MaxT showing the site.


https://twitter.com/JamesRambin
__________________
Follow The ATX on X:
https://twitter.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
     
  #67  
Old Posted Oct 4, 2019, 6:19 PM
MBAus MBAus is offline
Registered User
 
Join Date: Apr 2019
Posts: 35
They've put up more permanent construction barriers around this now and have closed off 17th St. on this block. They've been digging up the road today to do utility work but I expect they'll begin demo of the parking lot soon.
Reply With Quote
     
     
  #68  
Old Posted Oct 4, 2019, 6:29 PM
Jdawgboy's Avatar
Jdawgboy Jdawgboy is offline
Representing the ATX!!!
 
Join Date: Jan 2003
Location: Austin
Posts: 5,735
What's that crane for across from the Cambridge?
__________________
"GOOD TIMES!!!" Jerri Blank (Strangers With Candy)
Reply With Quote
     
     
  #69  
Old Posted Oct 4, 2019, 9:28 PM
MichaelB MichaelB is online now
Registered User
 
Join Date: May 2006
Location: North edge of Downtown
Posts: 3,208
Quote:
Originally Posted by Jdawgboy View Post
What's that crane for across from the Cambridge?
Travis County Courthouse
Reply With Quote
     
     
  #70  
Old Posted Oct 29, 2019, 8:23 PM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Where the lights are much brighter
Posts: 12,045
The tower crane is scheduled to go up the weekend of 12/06-12/09.

https://abc.austintexas.gov/web/perm...ertyrsn=253176

There have been a lot of permits filed related to utilities which may be the reason for the apparent groundbreaking delay.
__________________
Follow The ATX on X:
https://twitter.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
     
  #71  
Old Posted Dec 2, 2019, 4:52 PM
MBAus MBAus is offline
Registered User
 
Join Date: Apr 2019
Posts: 35
Looks like the base for the crane is in.

Reply With Quote
     
     
  #72  
Old Posted Dec 5, 2019, 6:26 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,326
FAA permit for the building - 220 feet.

https://oeaaa.faa.gov/oeaaa/external...3488126&row=18
__________________
Conform or be cast out.
Reply With Quote
     
     
  #73  
Old Posted Dec 8, 2019, 2:54 PM
clayton_rogue clayton_rogue is offline
Registered User
 
Join Date: Oct 2019
Location: Austin, TX
Posts: 85
Looks like the crane is almost up.

Reply With Quote
     
     
  #74  
Old Posted Dec 9, 2019, 3:49 AM
IluvATX IluvATX is online now
Registered User
 
Join Date: Jan 2014
Location: Anchorage-Austin-Anchorage-Austin and so forth...
Posts: 1,189
I always thought the the Hilton garden inn chain was more suburban. Correct me if I’m wrong, but I stayed at one once and it was literally a 3 story building with courtyards.
Reply With Quote
     
     
  #75  
Old Posted Dec 9, 2019, 4:56 AM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Where the lights are much brighter
Posts: 12,045
Quote:
Originally Posted by IluvATX View Post
I always thought the the Hilton garden inn chain was more suburban. Correct me if I’m wrong, but I stayed at one once and it was literally a 3 story building with courtyards.
I think that's mostly true, except for the mid-rise versions like this one.
__________________
Follow The ATX on X:
https://twitter.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
     
  #76  
Old Posted Dec 9, 2019, 5:27 PM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,326
This will be our 2nd one, the other is the one next to the Sabine at 5th & I-35.
__________________
Conform or be cast out.
Reply With Quote
     
     
  #77  
Old Posted Dec 12, 2019, 1:59 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,326
FAA permit for the crane - 270 feet.

https://oeaaa.faa.gov/oeaaa/external...1155314&row=15
__________________
Conform or be cast out.
Reply With Quote
     
     
  #78  
Old Posted Dec 12, 2019, 2:12 AM
MichaelB MichaelB is online now
Registered User
 
Join Date: May 2006
Location: North edge of Downtown
Posts: 3,208
crane is complete......!
Too bad its not easier to post photos! LOL!
Reply With Quote
     
     
  #79  
Old Posted Feb 12, 2020, 2:40 AM
Urbannizer's Avatar
Urbannizer Urbannizer is online now
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,380
__________________
HAIF
Reply With Quote
     
     
  #80  
Old Posted Apr 30, 2020, 7:56 PM
Urbannizer's Avatar
Urbannizer Urbannizer is online now
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,380
__________________
HAIF
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > United States > Texas & Southcentral > Austin
Forum Jump



Forum Jump


All times are GMT. The time now is 10:30 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.