  #1981  
Old Posted Jun 25, 2020, 11:04 PM
bradnixon bradnixon is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,071
The info from the Rideau River Pedestrian Bridge session from earlier in the week is now online: https://ottawa.ca/en/planning-develo...estrian-bridge
Reply With Quote
     
     
  #1982  
Old Posted Jun 26, 2020, 7:26 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Registered User
 
Join Date: Mar 2012
Location: Ottawa
Posts: 10,894
Video of girder installation at the Airport Parkway. I'm unable to embed the video on the forum.

https://www.youtube.com/watch?time_c...ature=emb_logo

Video Link

Last edited by rocketphish; Jun 26, 2020 at 9:04 PM. Reason: Embedded video
Reply With Quote
     
     
  #1983  
Old Posted Jul 2, 2020, 7:23 PM
Baybreeze12 Baybreeze12 is offline
Registered User
 
Join Date: Aug 2018
Posts: 25
Does anyone know if there are numbers out on projected ridership once Stage 2 opens? I find it interesting that daily ridership right before the line shut down (and the pandemic) had climbed to almost 20k, which seems like a lot for such a neglected line!

For context, the Scarborough RT averages 35k (in 6.4km) daily, while the Sheppard Subway hits about 50k (in 5.5km), and those have considerably more infrastructure than Trillium.
Reply With Quote
     
     
  #1984  
Old Posted Jul 2, 2020, 7:29 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Registered User
 
Join Date: Mar 2012
Location: Ottawa
Posts: 10,894
Quote:
Originally Posted by Baybreeze12 View Post
Does anyone know if there are numbers out on projected ridership once Stage 2 opens? I find it interesting that daily ridership right before the line shut down (and the pandemic) had climbed to almost 20k, which seems like a lot for such a neglected line!

For context, the Scarborough RT averages 35k (in 6.4km) daily, while the Sheppard Subway hits about 50k (in 5.5km), and those have considerably more infrastructure than Trillium.
I don't remember seeing Stage 2 ridership numbers for Confederation or Trillium. Before the pandemic, I would have estimated Stage 2 ridership for Trillium to be around 30,000. That could go up fast within 10 years with significant TOD and the new Civic Hospital.

Because of the pandemic, fear and new work-from-home procedures, it might have a significant long-term impact on ridership.
Reply With Quote
     
     
  #1985  
Old Posted Jul 5, 2020, 3:29 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Registered User
 
Join Date: Mar 2012
Location: Ottawa
Posts: 10,894
O-Train South Extension - Construction Update
July 3, 2020



In the south, there is ongoing work at the Walkley Maintenance and Storage Facility (MSF) and on multiple rail bridges including Airport Parkway, Uplands Road, Lester Road, Leitrim Road, Bowesville Road, Earl Armstrong Road, and Limebank Road.

Existing Trillium Line:

Gladstone Station

▪ Rock excavation is underway through the use of hoe ramming and controlled blasting.

Carleton Station

▪ Work is starting at Carleton Station to create a laydown area. MUP and pedestrian detours will be implemented to reroute the public away from construction.

Dows Lake Tunnel

▪ Preparations are underway for the removal of rail in the Dows Lake Tunnel.
▪ Rail and track ties have been removed from outside the south entrance of the Dows Lake Tunnel.

Ellwood Diamond

▪ Crews have removed the northbound and southbound sections of rail and track ties to accommodate the construction of the new rail bridge between Mooney’s Bay Station and Walkley Station which will carry Line 2 over the VIA rail corridor.
▪ Caisson work is currently underway.

Walkley Maintenance and Storage Facility (MSF)

▪ Crews continue to work on the MSF Main Building foundations including concrete work for the light and heavy maintenance pits, elevator pits, grade beams and underfloor services.
▪ Civil works for the underground utilities including watermain, storm drainage and sanitary system are continuing.
▪ Rail removal near the MSF is underway.

Trillium Line South Extension:

Airport Parkway Rail Bridge

▪ Retaining wall construction is complete.
▪ Crews completed the installation of rail bridge girders during the daytime on June 16 and overnight on June 17.
▪ Precast concrete span girders are hoisted at night with a 500-tonne crane.

Airport Elevated Guideway

▪ 13 of 17 caissons have been poured to date.
▪ 8 of 17 columns have been poured to date.
▪ Column work is complete at the Airport loading dock and crews are constructing the pier cap.



Uplands Drive Rail Bridge

▪ Crews completed the installation of rail bridge girders overnight on June 8.
▪ Retaining wall construction continues.

Lester Road Rail Bridge

▪ Pier cap construction continues.
▪ Preparations are underway for installation of rail girders on July 2.


Bridge superstructure work continues at Lester Rail Bridge. Girder installation took place on July 2, 2020.

Leitrim Road Rail Bridge

▪ 2 of 4 caissons are complete. The 2 remaining north caissons are pending watermain reconfiguration.
▪ Preparations are underway for 2 of the 4 columns.
▪ Construction of retaining wall is underway.

Bowesville Road Rail Bridge

▪ Crews completed installation of rail bridge girder installation overnight on June 10.

Earl Armstrong Rail Bridge

▪ 4 of 4 caissons are complete.
▪ Work on 4 columns and pier caps continue.

Limebank Elevated Guideway

▪ 5 of 10 caissons are complete.
▪ Crews have started constructing 5 of 10 columns.
▪ Ground improvement work for the Limebank Road embankment continues.

Guideway between Leitrim Road and Earl Armstrong Road

▪ Ground improvement work is underway at the Earl Armstrong Road embankments.

Guideway between Hunt Club Road and Leitrim Road:

▪ Embankment work is ongoing.

https://mailchi.mp/95d2467ff0a5/o-tr...0?e=a999a549a3
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 9:41 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2020, vBulletin Solutions, Inc.