WarrenC12
Active member
RIP people who can't walk 2 minutes in the opposite direction.
Doesn't this forum complain when people have to cross the street to access a station?
RIP people who can't walk 2 minutes in the opposite direction.
Doesn't this forum complain when people have to cross the street to access a station?
Yeah, the 84 is the only service for 2nd between Cambie and Clark - it's not going anywhere.
I'm seeing three, maybe four future developments that would outright benefit from an entrance on 1st. The rest most likely won't mind walking on 2nd instead.
"Design transit facility building height, where appropriate, to increase transit visibility from the surrounding neighbourhood and to mark the location as a neighbourhood centre."
https://www.translink.ca/-/media/tr...g-the-transit-network/tpfdg-print-version.pdf
If anything there's more room for development on the south side of East 1st then anything between East 1st and the train tracks.
I'm kinda hoping for a future pedestrian bridge linking up all the segments of Thornton St, so that the future densification of Terminal Ave will have more options for skytrain connections.
This is/was the plan for the connections in the Flats
As these are freight yards rather than passenger trains (as is the case with Hudson Yards) it's unlikely it could ever be decked over for development.
Ventilation would be a big issue but it would be possible, bassicly the same as the waterfront hub idea. Not to say I believe this would ever happen, atlease not in the next 50 years.
I see no reason why being a freight yard makes a difference. Ventilation would be a big issue but it would be possible, bassicly the same as the waterfront hub idea. The bigger issue is the building foundations, the rail yard would need to be completely removed for construction.
The structural feasibility study included a preliminary investigation of the impacts on the rail yard likely to result from the
development anticipated in this framework document, using the Illustrative Concept Plan as a basis for the analysis. It
was initially thought that some portions of the rail tracks would be able to pass below the development sites, however on
further exploration it was determined that the required structural components for earthquake resistance would preclude
the ability to maintain rail lines under the buildings. The study concluded that there would be a loss of up to one third of
the existing rail track length within the yard to accommodate the development in the Illustrative Concept Plan.
I posted it just wrt the pedestrian bridges.
I could see them 'push launching' a bridge across the active rail yard the same way they did for the Coast Meridien Overpass (but on a much smaller/narrower scale).
Two bridges is going to be pricey - if plausible, City Hall may very well choose to scope-creep it into one big greenway from 1st to Northern.
Don't dream on it. The City can't even afford to take down the two viaducts. Looks like they will just let them rot and collapse.
A pedestrian / cyclist bridge would be much lighter than a road bridge, so you could also prefabricate it off site and then crane it into plane in a day or two like they did for the Commercial / Broadway platform 5 walkway. I recall broadway was only closed for a weekend for that operation.
November: Continuing bulk excavation on future station site; relocating utilities on Carolina Street and E. 1st Ave;
installing fencing around elevated guideway construction site; closing Earl Finning Way for water line relocation;
beginning installation of the elevated guideway columns; conducting geotechnical surveys; and installing monitoring
devices.
• December – Spring 2022: Continuing the construction of the elevated guideway columns
At GNW/Emily Carr
They started on Great Northern Way back in the 1980's...December – Spring 2022: Continuing the construction of the elevated guideway columns
Makes it sound like they've already started that..