Based on the contents of the long-term corridor plan, the following major components have been identified, in order of priority:
- Mainline Widening (in the form of a HOV lane)
- Glenmore Trail Interchange
- Anderson Road / Bow Bottom Trail Interchange Area including the Collector Distributor System
- 16 Avenue N.E. Interchange Improvements
- 50 Avenue S.E. Connector
- Memorial Drive to 17 Avenue S.E. Area
SHORT TERM (next 10 years):
Phase 1
• Add capacity to Deerfoot Trail in the form of a new buffer separated median High Occupancy Vehicle (HOV) lane in each direction between Barlow Trail
and Airport Trail.
• Other minor improvements including grade separating the entrance and exit ramps between Memorial Drive and 17 Avenue S.E. to remove weaving operations along Deerfoot Trail in both directions; providing a direct connection between 11 Street N.E. and Deerfoot Trail northbound which represents an element of the future full interchange; widening the northbound loop ramp from Deerfoot Trail to Anderson Road / Bow Bottom Trail to accommodate two lanes; and creating an early northbound exit ramp to Southland Drive – prior to the interchange at Anderson Road / Bow Bottom Trail to remove weaving operations along Deerfoot Trail between the two interchanges.
Phase 2
• Glenmore Trail Interchange improvements – including Heritage Drive and Blackfoot Trail interchange modifications
• Country Hills Boulevard Interchange improvements
• 128 Avenue N.E. Interchange
MEDIUM TERM (11 to 20 years):
Phase 3
• Anderson Road / Bow Bottom Trail Interchange improvements including
- Collector / Distributor System – between Barlow Trail and Southland Drive
- Southland Drive Interchange reconstruction
- 11 Street S.E. Interchange modifications (southbound)
- Heritage Meadows Way Interchange modifications (northbound)
- 24 Street S.E. Interchange modifications
- Barlow Trail Interchange modifications
Phase 4
• 16 Avenue N.E. interchange improvements
Deerfoot Trail to Barlow Trail
- 16 Avenue / 19 Street N.E. interchange
- 16 Avenue / Barlow Trail N.E. interchange reconfiguration
- New 16 Avenue N.E. overpass structure at Deerfoot Trail
LONG-TERM (beyond 20 years)
Phase 5
• 50 Avenue S.E. Connector
• Beddington Trail Interchange completion
• McKnight Boulevard Interchange improvements
• Airport Trail Interchange improvements
Phase 6
• Memorial Drive Interchange improvements
- Construct new Southbound to Eastbound ramp
- Remove existing at-grade intersections
• 17 Avenue S.E. Interchange
- Reconfigure interchange to align Blackfoot Trail to Barlow Trail
- Reconfigure Memorial Drive / Barlow Trail interchange
Total cost estimate of the Full Long Term Plan is $2.25 Billion
Full Report:
https://www.calgary.ca/content/dam/www/transportation/tp/documents/projects/current-planning-projects/deerfoot-study/deerfoot-trail-study-phase-4-final-recommendation-report-2020.pdf