Analysis: Ottawa's four-month old LRT system shouldn't have
this many problems already
JON WILLING Updated: January 20, 2020
OC Transpo had to deliver afternoon peak service
on the Confederation Line with three fewer trains
than usual Monday, with worries the train
shortage would continue Tuesday morning in
what has been an abysmal start of the year for the
$2.1-billion LRT system.
It’s almost as if the City of Ottawa is reaching a breaking point on the
durability of LRT and the performance of Rideau Transit Maintenance, an
offshoot of the Rideau Transit Group (RTG).
“They’re going to have to give us some straight goods here on the trains,”
transit chair Allan Hubley said Monday after calling a special meeting of
the transit commission for later this week to address the recent, and
unusual, LRT problems.
Only 10 of the usual 13 trains were available Monday afternoon, after
running the morning peak service with 11 trains.
Then, between the morning and afternoon service periods, two trains had
to be removed from the 12.5-kilometre rail line because one train had a
wheel problem and the other had a compressor problem.
The times between trains during peak service is four minutes when 13
trains are running.
With only 10 trains, wait times were increased by about
one minute and Transpo was predicting a 20-per-cent increase to the
number of people waiting on platforms and crammed into the trains.
The Tuesday morning peak service might also only have 10 trains, leading
Transpo to consider launching the replacement R1 bus service to help the
LRT system move customers.
It was the last thing Transpo needed after a five-day period that included
a broken overhead wire near St. Laurent Station and malfunctioning
switches during the weekend snowstorm.
John Manconi, the city’s general manager of transportation, sent a memo
to members of council and the transit commission saying city brass is
demanding RTG fix the problems with LRT.
Manconi’s memo talked about switch heaters as being one of the
problems.
This won’t be new to inspectors who watched RTG’s construction of the
Confederation Line and noted concerns with the switch heaters across
the entire rail system. This newspaper has reported on those inspection
documents (https://ottawacitizen.com/news/loca...ious-deficienciesin-lead-up-to-march-deadline) , including one document from last winter
that flagged the performance of switch heaters during heavy snowfall.
As Hubley pointed out, the problems in recent days have been particularly
strange.
“That’s not stuff that should be happening,” he said.
Should people expect a snapped overhead catenary system wire four
months into revenue service?
Probably not, but, as the public has been told, these things can happen.
Should heaters have problems keeping snow and ice off the track
switches during a snow storm?
Probably not, because inspectors told RTG to improve the devices during
the testing.
Should Transpo have to run LRT service, at one of the busiest times of
day, short three trains?
No, because there should be enough spare trains ready to go.
Central to the issue of trains is how many are actually revenue-service
ready.
It’s been a mystery how many Alstom Citadis Spirit trains of the
city’s order of 34 LRT vehicles for Stage 1 are fully functional.
First, the city said it needed 15 double-vehicle trains (so, 30 vehicles
connected in pairs) to satisfy peak-period service.
That number was
decreased to 13 double-vehicle trains, based on actual ridership numbers,
which would suggest there’s a solid standby fleet.
Yet, RTG couldn’t produce 13 double-car trains for the Monday afternoon
peak service, adding time to the train headways, during a frostbite
advisory.
Hubley agreed that an explanation is warranted at the transit commission
meeting, which has been scheduled for Thursday afternoon.
If RTG is having trouble keeping an operational fleet available each day,
there could be an unwillingness from Transpo to add more trains into
regular service and decrease the wait times.
There’s no point raising in
the expectations of customers only to fail meeting a new standard.
The Christmas and New Year holiday period was a chance for RTG to get
ahead on its maintenance regime with a reduced ridership, but not even
three weeks into the year it’s being called on the carpet by its client to
explain why it can’t meet its contract commitments so early in their 30-
year maintenance agreement.
Failing Transpo’s LRT service standards continues to financially hurt RTG,
which isn’t getting its monthly payment from the city because of the
problems.
RTG acknowledged receipt of an email with two technical questions this
newspaper had Monday, but as of deadline there were no answers.
The questions were about the reasons for the train shortage and the switch
problems.
Hubley said by calling a special meeting of the transit commission for
later in the week — a meeting he expects will include RTG — he hopes it
will give the company time to stabilize service, or at least have a plan.
“It upsets me a lot. Why are we going through this when it can be so easily
prevented?” Hubley said.
“It takes your words away. This is what they’re well-paid to do.
Why aren’t they getting it done for us?”
https://ottawacitizen.com/news/local-news/analysis-ottawas-four-month-old-lrt-system-shouldnt-have-this-many-problems-already