PHILADELPHIA | Comcast Technology Center | 1,121 FT | 60 FLOORS


Morning (7AM) of 11/13/2015:

K0vXopK.jpg
 
Its still not clear (to me at least) what is going on with the temporary supports. These are installed to support that large steel beam that is being set in place today? Will a permanent column be installed later?
 
Its still not clear (to me at least) what is going on with the temporary supports. These are installed to support that large steel beam that is being set in place today? Will a permanent column be installed later?

Yes that beam is part of the roof of the atrium on the east side. This render is what it'll look like:

comcast_entrance_1024.jpg


As you can see there's members in there that won't be supported by the core of the structure and that's why they need the temporary supports.
 
The top of the core is starting to become visible at different points throughout the city! For example, you can see at the intersection of 18th and Walnut.
 
Yes that beam is part of the roof of the atrium on the east side. This render is what it'll look like:

comcast_entrance_1024.jpg


As you can see there's members in there that won't be supported by the core of the structure and that's why they need the temporary supports.

--

It'll be very interesting to see how they treat the fenestration on that entrance since (firstly) glazing cannot be manufactured in that size and secondly, even with structural sealant between glass, they'll need additional framing or fittings. I'm sure the final result will be much different in aesthetics than the renderings present.

My hunch regarding the temporary shoring is similar - probably there to help support the steel framing for the roof (may also assist with installation of the soffit too).
 
--

It'll be very interesting to see how they treat the fenestration on that entrance since (firstly) glazing cannot be manufactured in that size and secondly, even with structural sealant between glass, they'll need additional framing or fittings. I'm sure the final result will be much different in aesthetics than the renderings present.

My hunch regarding the temporary shoring is similar - probably there to help support the steel framing for the roof (may also assist with installation of the soffit too).

If Foster + Partners had two pence for every time they heard that....

Outrageous fenestration, and pushing those boundaries, is what they're known for. With a project this big, I assume they'll want to push again.
 
--
It'll be very interesting to see how they treat the fenestration on that entrance since (firstly) glazing cannot be manufactured in that size and secondly, even with structural sealant between glass, they'll need additional framing or fittings. I'm sure the final result will be much different in aesthetics than the renderings present.

Good point. I'm envisioning (hoping for!) something like the ends of the Kimmel Center's barrel vaulted roof:

depositphotos_9835881-Dome---Kimmel-Center.jpg


That to me would look seamless enough to capture the same look as a single, continuous piece of glass.
 
I completely overlooked this iconic landmark! This would seem a very viable treatment to keep the entrance appearing as clean as in the rendering. Good call!
 
Would anyone like to predict the height of the core by New Year's eve?

In other words, how tall will the core reach when the Mummer's strut down Broad Street?
 
Its still not clear (to me at least) what is going on with the temporary supports. These are installed to support that large steel beam that is being set in place today? Will a permanent column be installed later?

The fabricated beams are being set in two pieces each. So the temporary mast in the middle is there to support each half until they are joined together. once joined the mast can be removed and the beams will be supported only on each end.
 
I think it can. A casual look makes it appear as there would be narrow panes of vertical glass the entire length of the bumpout entrance. But that's not the case. It will not be panes that are 40 feet tall. Closer inspections shows horizontal etching across the width. It's more evident in a render pictured right outside the building site.



--

It'll be very interesting to see how they treat the fenestration on that entrance since (firstly) glazing cannot be manufactured in that size and secondly, even with structural sealant between glass, they'll need additional framing or fittings. I'm sure the final result will be much different in aesthetics than the renderings present.

My hunch regarding the temporary shoring is similar - probably there to help support the steel framing for the roof (may also assist with installation of the soffit too).
 